747 S CURSON AVE 90036

Certificate Information: 747 S CURSON AVE 90036

Application / Permit
18016-10000-20974
Plan Check / Job No.
B18LA13345
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 6 CANTILEVER COLUMNS. (Installation of four columns at south elevation and two columns at east elevation; all to be finished in stucco to match existing in color and texture. Any exterior alterations at the areas of retrofit work shall be replaced in-kind to match the existing exterior of the structure in material, color, and texture. There shall be no other alterations to existing structure(s), landscape, or hardscape.)
Permit Issued
Issued on 7/10/2020
Issuing Office
Current Status
CofC Issued on 10/20/2020

Permit Application Status History

Submitted 6/29/2018 APPLICANT
Assigned to Plan Check Engineer 8/16/2018 MONICA RAMIREZ
Corrections Issued 8/21/2018 MONICA RAMIREZ
Quality Review Completed 8/23/2018 SAI KHUM
Building Plans Picked Up 9/7/2018 APPLICANT
Applicant returned to address corrections 1/15/2019 MONICA RAMIREZ
Applicant returned to address corrections 3/19/2019 MONICA RAMIREZ
Plan Check Approved 5/6/2019 MONICA RAMIREZ
Issued 7/10/2020 APPLICANT
OK for CofC 8/26/2020 DARRYL ARNOLD
CofC Issued 10/20/2020 TERRY HERR

Permit Application Clearance Information

HPOZ Cleared 4/30/2019 CHRISTINA PARK
Housing rent stabilization Cleared 6/18/2020 MICHAEL SOTO

Contact Information

Contractor Zebra Construction Inc; Lic. No.: 1055609-B 145 S FAIRFAX STE 200/300      LOS ANGELES, CA 90036
Engineer Roberts, Jeffrey Allan; Lic. No.: C56881 9925 COMMERCE AVENUE SUITE B      TUJUNGA, CA 91042

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/16/2020 Partial Approval DARRYL ARNOLD
Deputy Other (see comments) 8/4/2020 Approved DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 8/6/2020 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 8/6/2020 Approved DARRYL ARNOLD
Structural Steel Frame 8/6/2020 Approved DARRYL ARNOLD
Wood Frame 8/6/2020 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 8/7/2020 Conditional Approval DARRYL ARNOLD
Wood Frame 8/7/2020 Corrections Issued VAHE KELEDJIAN
Floor/Roof Diaphrgm/Shear Wall 8/11/2020 Approved DARRYL ARNOLD
Wood Frame 8/11/2020 Not Ready for Inspection DARRYL ARNOLD
Interior/Exterior Lathing 8/14/2020 Approved DARRYL ARNOLD
Final 8/26/2020 OK for CofC DARRYL ARNOLD
METHANE-Final 8/26/2020 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/26/2020 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 8/26/2020 Approved DARRYL ARNOLD