45 E MARKET ST 90291

Certificate Information: 45 E MARKET ST 90291

Application / Permit
18016-10000-20867
Plan Check / Job No.
B18LA13240
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(1) Dwelling - Single Family
Work Description
REVISE STAIR AT THE REAR OF BUILDING FROM CIRCULAR TO SWITCHBACK STAIR. THIS WORK IS SUPPLEMENTAL TO 14014-10000-04696.
Permit Issued
Issued on 11/16/2018
Issuing Office
Metro
Current Status
Permit Finaled on 11/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2018 APPLICANT
Assigned to Plan Check Engineer 7/19/2018 JOHN VASQUEZ
Corrections Issued 7/24/2018 JOHN VASQUEZ
Quality Review Completed 7/26/2018 CHARLES CHANG
Building Plans Picked Up 7/31/2018 APPLICANT
Disabled Access Plans Picked Up 7/31/2018 APPLICANT
Applicant returned to address corrections 10/18/2018 JOHN VASQUEZ
Plan Check Approved 11/16/2018 JOHN VASQUEZ
Issued 11/16/2018 LADBS
Permit Finaled 11/21/2024 FARHAD DADBIN

Permit Application Clearance Information

DAS Clearance Cleared 7/6/2018 WAI LAU
Specific Plan Cleared 8/1/2018 JEFF KHAU
Specific Plan Cleared 8/2/2018 EDER ROMERO
Specific Plan Cleared 8/2/2018 EDER ROMERO
Coastal Zone Cleared 8/7/2018 DENNIS CHEW
Eng Process Fee Ord 176,300 Cleared 8/7/2018 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/7/2018 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/7/2018 LEE GUILBEAUX
Public Works-Sewers Cleared 8/7/2018 LEE GUILBEAUX
Fire Marshall Fire Life Safety Cleared 9/20/2018 DOMINIQUE MEDINA

Contact Information

Architect Soderbergh, Lars Gustaf; Lic. No.: C13554 1738 BERKELEY STREET      SANTA MONICA, CA 90404
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/22/2019 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 3/15/2019 Approved JASON BORUTA
Footing/Foundation/Slab 3/15/2019 Approved JASON BORUTA
Reinforced Concrete Frame 3/29/2019 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 5/17/2019 Approved JASON BORUTA
Reinforced Concrete Frame 5/17/2019 Approved JASON BORUTA
Reinforced Concrete Frame 6/24/2019 Approved JASON BORUTA
Wood Frame 10/16/2019 Partial Approval JASON BORUTA
Pre-Inspection 2/6/2023 Corrections Issued SORIN CIRSTOIU
Pre-Inspection 2/6/2023 Not Ready for Inspection FARHAD DADBIN
Final 11/21/2024 Permit Finaled FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 11/21/2024 Approved FARHAD DADBIN