4520 N LOWELL AVE 90032

Certificate Information: 4520 N LOWELL AVE 90032

Application / Permit
18016-10000-20034
Plan Check / Job No.
B18LA12646
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93 USING STEEL MOMENT FRAME
Permit Issued
Issued on 2/5/2020
Issuing Office
Metro
Current Status
CofC Issued on 7/9/2020

Permit Application Status History

Submitted 6/28/2018 APPLICANT
Assigned to Plan Check Engineer 8/15/2018 HANS SANTIAGO
Corrections Issued 8/22/2018 HANS SANTIAGO
Quality Review Completed 8/24/2018 SAI KHUM
Building Plans Picked Up 9/26/2018 APPLICANT
Plan Check Approved 4/30/2019 Andrew Santiago
Issued 2/5/2020 LADBS
OK for CofC 6/24/2020 MARK FERRARI
CofC Issued 7/9/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 2/5/2020 MICHAEL GREGERSON

Contact Information

Contractor L A Retrofit Inc; Lic. No.: 1047943-B 818 7TH STREET APARTMENT 2      SANTA MONICA, CA 90403
Engineer Farmand, Anthony E; Lic. No.: C62595 4675 MACARTHUR COURT SUITE 800      NEWPORT BEACH, CA 92660

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2020 Not Ready for Inspection MARK FERRARI
Pre-Inspection 2/10/2020 Partial Approval MARK FERRARI
Wood Frame 2/10/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 2/11/2020 Partial Approval MARK FERRARI
Deputy Wood Construction 2/18/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 2/26/2020 Corrections Issued MARK FERRARI
Wood Frame 2/26/2020 Approved MARK FERRARI
Excavation/Setback/Form/Re-Bar 3/3/2020 Approved MARK FERRARI
Footing/Foundation/Slab 3/3/2020 Approved MARK FERRARI
Deputy Reinf. Concrete 3/5/2020 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 3/10/2020 Corrections Issued MARK FERRARI
Final 4/1/2020 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 4/1/2020 SGSOV Not Ready MARK FERRARI
Smoke Detectors 4/1/2020 Approved MARK FERRARI
Final 6/24/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 6/24/2020 SGSOV Approved MARK FERRARI