2515 W OCEAN VIEW AVE 90057

Certificate Information: 2515 W OCEAN VIEW AVE 90057

Application / Permit
18016-10000-19839
Plan Check / Job No.
B18LA12526
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS
Permit Issued
Issued on 7/16/2020
Issuing Office
Current Status
CofC Issued on 7/23/2021

Permit Application Status History

Submitted 6/21/2018 APPLICANT
Assigned to Plan Check Engineer 7/19/2018 MANUEL MONTUFAR
Corrections Issued 7/24/2018 MANUEL MONTUFAR
Quality Review Completed 7/25/2018 SAI KHUM
Building Plans Picked Up 7/26/2018 APPLICANT
Applicant returned to address corrections 8/7/2018 MANUEL MONTUFAR
Plan Check Approved 8/28/2018 MANUEL MONTUFAR
Issued 7/16/2020 APPLICANT
OK for CofC 7/23/2021 MARK FERRARI
CofC Issued 7/23/2021 WINSTON DUNNING

Permit Application Clearance Information

Abandoned oil well Cleared 8/7/2018 ROBERT DUFF
Abandoned oil well approval Cleared 8/7/2018 ROBERT DUFF
Project located in CRA area Cleared 8/14/2018 JIM URQUHART
Housing rent stabilization Cleared 7/13/2020 STEVEN HOFSTAD

Contact Information

Contractor Par Construction Inc; Lic. No.: 983593-B 12319 GREENE AVE      LOS ANGELES, CA 90066
Engineer Funk, David Lyle; Lic. No.: S5421 619 BERYL ST      REDONDO BEACH, CA 90277

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/3/2020 Approved DARRYL ARNOLD
Wood Frame 10/21/2020 Approved DARRYL ARNOLD
Wood Frame 11/30/2020 Partial Approval MARK FERRARI
Deputy Steel/Welding 12/10/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 12/11/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 12/14/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 12/14/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 12/16/2020 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 12/16/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 12/16/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 12/17/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 12/17/2020 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 12/21/2020 Corrections Issued MARK FERRARI
Insulation 12/21/2020 Approved MARK FERRARI
Structural Steel Frame 12/21/2020 Partial Approval MARK FERRARI
Wood Frame 12/21/2020 Corrections Issued MARK FERRARI
Deputy Reinf. Concrete 12/22/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 12/23/2020 Conditional Approval MARK FERRARI
Deputy Wood Construction 1/5/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 3/3/2021 Not Ready for Inspection DARRYL ARNOLD
Structural Steel Frame 3/3/2021 Not Ready for Inspection DARRYL ARNOLD
Wood Frame 3/3/2021 Corrections Issued DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 3/8/2021 Approved MARK FERRARI
Structural Steel Frame 3/8/2021 Approved MARK FERRARI
Wood Frame 3/8/2021 Approved MARK FERRARI
Insulation 3/12/2021 Not Ready for Inspection DARRYL ARNOLD
Interior/Exterior Lathing 3/12/2021 Not Ready for Inspection DARRYL ARNOLD
Interior/Exterior Lathing 3/15/2021 Approved DARRYL ARNOLD
Final 4/6/2021 Corrections Issued MARK FERRARI
METHANE-Final 4/6/2021 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 4/6/2021 SGSOV Not Ready MARK FERRARI
Smoke Detectors 4/6/2021 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 6/29/2021 SGSOV Approved BRUCE CAMPBELL
Final 6/30/2021 Conditional Approval MARK FERRARI
SGSOV-Seismic Gas S/O Valve 6/30/2021 SGSOV Approved MARK FERRARI
Final 7/9/2021 Conditional Approval MARK FERRARI
Final 7/23/2021 OK for CofC MARK FERRARI