2515 W OCEAN VIEW AVE 90057
Certificate Information: 2515 W OCEAN VIEW AVE 90057
- Application / Permit
- 18016-10000-19839
- Plan Check / Job No.
- B18LA12526
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 7/16/2020
- Issuing Office
- Current Status
- CofC Issued on 7/23/2021
Permit Application Status History
| Submitted | 6/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2018 | MANUEL MONTUFAR |
| Corrections Issued | 7/24/2018 | MANUEL MONTUFAR |
| Quality Review Completed | 7/25/2018 | SAI KHUM |
| Building Plans Picked Up | 7/26/2018 | APPLICANT |
| Applicant returned to address corrections | 8/7/2018 | MANUEL MONTUFAR |
| Plan Check Approved | 8/28/2018 | MANUEL MONTUFAR |
| Issued | 7/16/2020 | APPLICANT |
| OK for CofC | 7/23/2021 | MARK FERRARI |
| CofC Issued | 7/23/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 8/7/2018 | ROBERT DUFF |
| Abandoned oil well approval | Cleared | 8/7/2018 | ROBERT DUFF |
| Project located in CRA area | Cleared | 8/14/2018 | JIM URQUHART |
| Housing rent stabilization | Cleared | 7/13/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Par Construction Inc; Lic. No.: 983593-B | 12319 GREENE AVE LOS ANGELES, CA 90066 |
| Engineer | Funk, David Lyle; Lic. No.: S5421 | 619 BERYL ST REDONDO BEACH, CA 90277 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/3/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 10/21/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/30/2020 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/10/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/11/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/14/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/14/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/16/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 12/16/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/16/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/17/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/17/2020 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2020 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 12/21/2020 | Corrections Issued | MARK FERRARI |
| Insulation | 12/21/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 12/21/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 12/21/2020 | Corrections Issued | MARK FERRARI |
| Deputy Reinf. Concrete | 12/22/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/23/2020 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 1/5/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 3/3/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Structural Steel Frame | 3/3/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 3/3/2021 | Corrections Issued | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 3/8/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 3/8/2021 | Approved | MARK FERRARI |
| Wood Frame | 3/8/2021 | Approved | MARK FERRARI |
| Insulation | 3/12/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/12/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/15/2021 | Approved | DARRYL ARNOLD |
| Final | 4/6/2021 | Corrections Issued | MARK FERRARI |
| METHANE-Final | 4/6/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 4/6/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Approved | BRUCE CAMPBELL |
| Final | 6/30/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 6/30/2021 | SGSOV Approved | MARK FERRARI |
| Final | 7/9/2021 | Conditional Approval | MARK FERRARI |
| Final | 7/23/2021 | OK for CofC | MARK FERRARI |