200 WORLD WAY 90045
Certificate Information: 200 WORLD WAY 90045
- Application / Permit
- 18016-10000-19522
- Plan Check / Job No.
- B18LA12328
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- Architectural and structural alterations to Terminal 2 which include office area revisions, hold room seating changes and addition of concession spaces (PH1F).
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2018 | SUEN LIEU |
| Corrections Issued | 9/7/2018 | SUEN LIEU |
| Quality Review Completed | 9/11/2018 | CHARLES CHANG |
| Plan Check Approved | 6/10/2021 | RODOLFO ARIAS |
| Issued | 7/14/2021 | APPLICANT |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| CofO in Progress | 12/19/2024 | ALAN NOVAK |
| Permit Finaled | 1/10/2025 | NICK LAROCCA |
| CofO Issued | 1/10/2025 | NICK LAROCCA |
| Permit Finaled | 1/10/2025 | NICK LAROCCA |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 10/22/2019 | HAROOT AVANESIAN |
| Project Permit | Cleared | 10/22/2019 | SUEN LIEU |
| Low Impact Development | Cleared | 1/30/2020 | AMMAR ELTAWIL |
| Stormwater Pollution Mitigatn | Cleared | 1/30/2020 | AMMAR ELTAWIL |
| Hydrant and Access approval | Cleared | 3/16/2020 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/10/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 2/17/2021 | PEDRO AYALA |
| Green Code | Cleared | 2/23/2021 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 3/10/2021 | SUEN LIEU |
| Building over 36-ft | Cleared | 3/24/2021 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 3/24/2021 | CALOSHA APPROVED |
| Airport buildings | Cleared | 5/20/2021 | ANDREW KO |
| Fire Marshall Fire Life Safety | Cleared | 5/20/2021 | ANDREW KO |
Contact Information
| Architect | Circenis,, John Robert; Lic. No.: C24596 | 1133 24TH #13 SANTA MONICA, CA 90403 |
| Contractor | Hensel Phelps Construction Co; Lic. No.: 1020262-B | 420 SIXTH AVENUE GREELEY, CO 80631 |
| Engineer | Mino,, Trevor Joseph; Lic. No.: C79257 | 3754 BRILLIANT DR LOS ANGELES, CA 90065 |
| Engineer | Moyle,, Ted Roger; Lic. No.: FP1867 | 1102 12TH ST UNIT 4 SANTA MONICA, CA 90403 |
| Engineer | Rees,, Simon; Lic. No.: S4897 | 1246 11TH ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 8/16/2021 | Not Ready for Inspection | ALAN NOVAK |
| Insulation | 8/16/2021 | Not Ready for Inspection | ALAN NOVAK |
| Light Gage Steel Frame | 8/16/2021 | Not Ready for Inspection | ALAN NOVAK |
| Final | 8/30/2021 | Not Ready for Inspection | ALAN NOVAK |
| Green Building Final | 8/30/2021 | Approved | ALAN NOVAK |
| Green Building Rough | 8/30/2021 | Approved | ALAN NOVAK |
| Light Gage Steel Frame | 8/30/2021 | Approved | ALAN NOVAK |
| Reinforced Concrete Frame | 8/30/2021 | Approved | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 8/30/2021 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 8/30/2021 | Approved | ALAN NOVAK |
| Light Gage Steel Frame | 8/31/2021 | Off-Hour Fees Due | |
| T-Bar Ceiling | 9/30/2021 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 10/1/2021 | Not Ready for Inspection | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 10/2/2021 | Partial Approval | ALAN NOVAK |
| Drywall Nailing | 10/8/2021 | Partial Approval | JONATHAN ALLEN |
| Excavation/Setback/Form/Re-Bar | 10/8/2021 | Partial Approval | JONATHAN ALLEN |
| Final | 10/8/2021 | Partial Approval | JONATHAN ALLEN |
| Excavation/Setback/Form/Re-Bar | 10/25/2021 | Partial Approval | ALAN NOVAK |
| Final | 11/2/2021 | Not Ready for Inspection | JONATHAN ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Partial Approval | ALAN NOVAK |
| Insulation | 12/17/2021 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 1/20/2022 | Partial Approval | JONATHAN ALLEN |
| Excavation/Setback/Form/Re-Bar | 2/2/2022 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 2/9/2022 | Partial Approval | ALAN NOVAK |
| Deputy Steel/Welding | 2/18/2022 | Approved | NICK LAROCCA |
| Final | 3/29/2022 | Not Ready for Inspection | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Approved | ALAN NOVAK |
| Wood Frame | 4/19/2022 | Approved | ALAN NOVAK |
| Deputy Steel/Welding | 8/31/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/1/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/2/2022 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 9/7/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/8/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/9/2022 | Conditional Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 3/1/2023 | Partial Approval | ALAN NOVAK |
| Deputy Other (see comments) | 3/6/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Other (see comments) | 3/17/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 3/28/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Other (see comments) | 5/1/2023 | Conditional Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 5/18/2023 | Partial Approval | ALAN NOVAK |
| Final | 8/29/2023 | Not Ready for Inspection | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 9/28/2023 | Partial Approval | ALAN NOVAK |
| Deputy Other (see comments) | 3/13/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Other (see comments) | 3/14/2024 | Conditional Approval | ALAN NOVAK |
| Final | 7/1/2024 | OK for TCO | ALAN NOVAK |
| Final | 7/5/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Fireproofing | 10/4/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Other (see comments) | 10/16/2024 | Conditional Approval | ALAN NOVAK |
| Final | 12/18/2024 | OK to Issue CofO | ALAN NOVAK |
| Pre-Inspection | 1/6/2025 | Approved | ALAN NOVAK |
| Pre-Inspection | 1/9/2025 | Approved | ALAN NOVAK |