524 W 17TH ST 90731
Certificate Information: 524 W 17TH ST 90731
- Application / Permit
- 18016-10000-19151
- Plan Check / Job No.
- B18LA12061
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-story retrofit per LAMC division 93, install 2SSCC
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 11/4/2020
Permit Application Status History
| Submitted | 6/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2018 | SAMUEL GONZALEZ |
| Corrections Issued | 7/23/2018 | SAMUEL GONZALEZ |
| Quality Review Completed | 7/25/2018 | SAI KHUM |
| Building Plans Picked Up | 7/26/2018 | APPLICANT |
| Plan Check Approved | 8/7/2018 | SAMUEL GONZALEZ |
| Issued | 3/18/2020 | LADBS |
| OK for CofC | 11/4/2020 | JOEY BUCHANAN |
| CofC Issued | 11/4/2020 | NICK LAROCCA |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/26/2020 | MICHAEL GREGERSON |
Contact Information
| Engineer | Funk, David Lyle; Lic. No.: S5421 | 619 BERYL ST REDONDO BEACH, CA 90277 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/26/2020 | Corrections Issued | JOEY BUCHANAN |
| Deputy Steel/Welding | 4/8/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 4/14/2020 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 4/15/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/15/2020 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 4/15/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 4/15/2020 | Approved | JOEY BUCHANAN |
| Final | 10/28/2020 | Conditional Approval | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 10/28/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 10/28/2020 | Approved | JOEY BUCHANAN |
| Final | 11/4/2020 | OK for CofC | JOEY BUCHANAN |