4575 W FINLEY AVE 90027
Certificate Information: 4575 W FINLEY AVE 90027
- Application / Permit
- 18016-10000-19038
- Plan Check / Job No.
- B18LA11981
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PR LABC DIV. 93 USING SCCS
- Permit Issued
- Issued on 2/4/2021
- Issuing Office
- Current Status
- CofC Issued on 7/26/2021
Permit Application Status History
| Submitted | 6/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2018 | SAMUEL GONZALEZ |
| Corrections Issued | 7/16/2018 | SAMUEL GONZALEZ |
| Quality Review Completed | 7/16/2018 | SAI KHUM |
| Building Plans Picked Up | 7/18/2018 | APPLICANT |
| Plan Check Approved | 9/5/2018 | SAMUEL GONZALEZ |
| Issued | 2/4/2021 | APPLICANT |
| OK for CofC | 7/23/2021 | BRUCE CAMPBELL |
| CofC Issued | 7/26/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/29/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers, Joe Alan; Lic. No.: C71535 | 1626 S MAYFLOWER AVE UNIT B MONROVIA, CA 91016 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/19/2021 | Approved | MARK FERRARI |
| Deputy Drilled-In Anchors | 3/2/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 3/2/2021 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/2/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 3/2/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Structural Steel Frame | 3/11/2021 | Conditional Approval | JONATHAN QUACH |
| Wood Frame | 3/11/2021 | Corrections Issued | JONATHAN QUACH |
| Interior/Exterior Lathing | 4/23/2021 | Conditional Approval | JONATHAN QUACH |
| Interior/Exterior Lathing | 5/7/2021 | Approved | JONATHAN QUACH |
| Final | 6/23/2021 | Corrections Issued | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 6/23/2021 | SGSOV Not Ready | BRUCE CAMPBELL |
| Smoke Detectors | 6/23/2021 | Approved | BRUCE CAMPBELL |
| Final | 7/23/2021 | OK for CofC | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Approved | BRUCE CAMPBELL |