5712 W LEXINGTON AVE 90038
Certificate Information: 5712 W LEXINGTON AVE 90038
- Application / Permit
- 18016-10000-18972
- Plan Check / Job No.
- B18LA11926
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93, INSTALL STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- CofC Issued on 11/8/2021
Permit Application Status History
| Submitted | 6/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2018 | MANUEL MONTUFAR |
| Corrections Issued | 8/7/2018 | MANUEL MONTUFAR |
| Quality Review Completed | 8/9/2018 | SAI KHUM |
| Building Plans Picked Up | 8/16/2018 | APPLICANT |
| Applicant returned to address corrections | 10/18/2018 | MANUEL MONTUFAR |
| Plan Check Approved | 10/23/2018 | MANUEL MONTUFAR |
| Issued | 2/3/2021 | APPLICANT |
| OK for CofC | 11/8/2021 | WINSTON DUNNING |
| CofC Issued | 11/8/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 10/19/2018 | JIM URQUHART |
| Housing rent stabilization | Cleared | 9/21/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hosseinzadeh, Jamshid K; Lic. No.: S3761 | 16808 ARMSTRONG AVE WD PARTNERS IRVINE, CA 92606 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/26/2021 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 3/31/2021 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 3/31/2021 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 4/6/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 4/23/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 5/13/2021 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 5/13/2021 | Approved | MARK FERRARI |
| Deputy Drilled-In Anchors | 7/21/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 7/21/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 7/22/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 7/22/2021 | Conditional Approval | BRUCE CAMPBELL |
| Structural Steel Frame | 8/13/2021 | Approved | BRUCE CAMPBELL |
| Wood Frame | 8/19/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Wood Construction | 8/20/2021 | Conditional Approval | MARK FERRARI |
| Drywall Nailing | 9/2/2021 | Approved | BRUCE CAMPBELL |
| Final | 9/24/2021 | Corrections Issued | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Not Ready | BRUCE CAMPBELL |
| Smoke Detectors | 9/24/2021 | Corrections Issued | BRUCE CAMPBELL |
| Final | 11/8/2021 | OK for CofC | WINSTON DUNNING |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Approved | WINSTON DUNNING |
| Smoke Detectors | 11/8/2021 | Approved | WINSTON DUNNING |