802 S BROADWAY 90014
Certificate Information: 802 S BROADWAY 90014
- Application / Permit
- 18016-10000-18358
- Plan Check / Job No.
- B18LA11500
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- CHANGE OF USE FROM THEATER TO RETAIL. TENANT IMPROVMENT FOR A NEW RETAIL STORE AND VOLUNTARY SEISMIC STRENGTHENING OF PORTION OF THE (E) BUILDING.
- Permit Issued
- Issued on 6/5/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2018 | LARRY LEE |
| Corrections Issued | 7/20/2018 | LARRY LEE |
| Quality Review Completed | 7/24/2018 | CHARLES CHANG |
| Building Plans Picked Up | 7/25/2018 | APPLICANT |
| Applicant returned to address corrections | 8/8/2018 | LARRY LEE |
| Applicant returned to address corrections | 11/15/2018 | LARRY LEE |
| Applicant returned to address corrections | 1/15/2019 | LARRY LEE |
| Plan Check Approved | 5/28/2019 | LARRY LEE |
| Plan Check Approved | 6/5/2019 | LARRY LEE |
| Issued | 6/5/2019 | LADBS |
| TCO Issued (Expire Date: 10-19-2021) | 4/22/2021 | ERNESTO CORRAL |
| CofO in Progress | 6/11/2021 | ERNESTO CORRAL |
| CofO Issued | 6/11/2021 | ERNESTO CORRAL |
| Permit Finaled | 6/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/9/2018 | CELINA MORENO |
| ZA Case | Cleared | 8/9/2018 | YOVANA PEREZ |
| ZA Case | Cleared | 8/9/2018 | YOVANA PEREZ |
| ZA Case | Cleared | 8/9/2018 | YOVANA PEREZ |
| ZA Case | Cleared | 8/9/2018 | YOVANA PEREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2018 | JEANETTE VONG |
| Marquee approval - CUL | Cleared | 1/16/2019 | HAROOT AVANESIAN |
| City Hist. Cultural Monument | Cleared | 3/4/2019 | LAMBERT GIESSINGER |
| Green Code | Cleared | 3/14/2019 | SARAH ABOULHOSN |
| Historical monument | Cleared | 3/15/2019 | JIM URQUHART |
| Project located in CRA area | Cleared | 3/15/2019 | JIM URQUHART |
| "Q" conditions | Cleared | 4/17/2019 | LATANYA ROUX |
| Supp. Use District POD/CDO/TDO | Cleared | 4/17/2019 | LATANYA ROUX |
| ZI | Cleared | 4/17/2019 | LATANYA ROUX |
| Encroachment in public way | Cleared | 4/19/2019 | KAREN LE |
| DAS Clearance | Cleared | 5/15/2019 | CHOI YAN |
| Fire Marshall Fire Life Safety | Cleared | 5/16/2019 | DOMINIQUE MEDINA |
| Building over 3-story or 36-ft | Cleared | 5/28/2019 | CALOSHA APPROVED |
Contact Information
| Architect | Gerod,, Debra A; Lic. No.: C23665 | GRUEN ASSOCIATES 6330 SAN VICENTE BLVD. STE. 200 LOS ANGELES, CA 90048 |
| Contractor | Shawmut Woodworking & Supply Inc; Lic. No.: 747583-B | 560 HARRISON AVENUE BOSTON, MA 02118 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Structural Steel Frame | 11/4/2019 | Conditional Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 11/7/2019 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 11/7/2019 | Partial Approval | DANIEL COLLINS |
| METHANE-Barrier | 11/7/2019 | Approved | DANIEL COLLINS |
| METHANE-Subgrade | 11/7/2019 | Approved | DANIEL COLLINS |
| Reinforced Concrete Frame | 11/7/2019 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 11/14/2019 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/20/2019 | Conditional Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2019 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 12/13/2019 | Partial Approval | DANIEL COLLINS |
| Structural Steel Frame | 12/13/2019 | Partial Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 12/16/2019 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 12/16/2019 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2019 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 1/7/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 1/7/2020 | Partial Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 1/13/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 1/13/2020 | Partial Approval | DANIEL COLLINS |
| Structural Steel Frame | 1/22/2020 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2020 | Not Ready for Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 2/14/2020 | Partial Inspection | KATY RAMIREZ |
| Structural Steel Frame | 2/14/2020 | Partial Inspection | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 2/19/2020 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 3/19/2020 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 4/2/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 4/8/2020 | Partial Approval | DANIEL COLLINS |
| Structural Steel Frame | 4/8/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 4/17/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 4/17/2020 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 4/24/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 4/24/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Light Gage Steel Frame | 4/27/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 4/30/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/1/2020 | Conditional Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 5/4/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 5/5/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/6/2020 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 5/6/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/7/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 5/8/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 5/12/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 5/12/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 5/12/2020 | Conditional Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 5/12/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/13/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/14/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/15/2020 | Approved | KATY RAMIREZ |
| Footing/Foundation/Slab | 5/19/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 5/19/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 5/22/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Reinforced Concrete Frame | 5/22/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/27/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 5/27/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/28/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 5/29/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 6/2/2020 | Partial Approval | DANIEL COLLINS |
| Structural Steel Frame | 6/11/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 6/12/2020 | Conditional Approval | DANIEL COLLINS |
| Wood Frame | 6/16/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 6/29/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 7/7/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 7/7/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 7/16/2020 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 7/16/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 7/16/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 7/17/2020 | Conditional Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 7/20/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 7/20/2020 | Partial Approval | DANIEL COLLINS |
| Pre-Inspection | 7/22/2020 | Partial Inspection | DANIEL COLLINS |
| Light Gage Steel Frame | 8/4/2020 | Partial Inspection | DANIEL COLLINS |
| Light Gage Steel Frame | 8/13/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 8/18/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/19/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/20/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 8/20/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/21/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/25/2020 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 8/25/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 8/25/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/26/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/27/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/28/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 9/3/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 9/21/2020 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 9/21/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 9/21/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 9/22/2020 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 10/5/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 10/5/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/7/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/8/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 10/9/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/13/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 10/13/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/19/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 10/20/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 10/21/2020 | Conditional Approval | KATY RAMIREZ |
| Drywall Nailing | 10/22/2020 | Partial Approval | DANIEL COLLINS |
| Insulation | 10/22/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 10/22/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 10/30/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 10/30/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 10/30/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 11/4/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 11/12/2020 | Conditional Approval | DANIEL COLLINS |
| Insulation | 11/19/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 11/19/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/30/2020 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 12/3/2020 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 12/3/2020 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 12/9/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/9/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 12/14/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Drywall Nailing | 12/15/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/15/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 12/31/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/31/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 1/7/2021 | Partial Approval | DANIEL COLLINS |
| T-Bar Ceiling | 1/21/2021 | Partial Approval | DANIEL COLLINS |
| T-Bar Ceiling | 2/17/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Pre-Inspection | 2/26/2021 | Partial Approval | DANIEL COLLINS |
| Pre-Inspection | 3/11/2021 | Partial Inspection | DANIEL COLLINS |
| Smoke Detectors | 3/23/2021 | Approved | DANIEL COLLINS |
| Special/Order Compliance | 3/31/2021 | Partial Approval | DANIEL COLLINS |
| Green Building Final | 4/7/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Special/Order Compliance | 4/7/2021 | Partial Inspection | DANIEL COLLINS |
| Final | 4/13/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Footing/Foundation/Slab | 4/13/2021 | Approved | DANIEL COLLINS |
| Green Building Final | 4/13/2021 | Approved | DANIEL COLLINS |
| Green Building Rough | 4/13/2021 | Approved | DANIEL COLLINS |
| METHANE-Final | 4/13/2021 | Approved | DANIEL COLLINS |
| METHANE-Rough | 4/13/2021 | Approved | DANIEL COLLINS |
| Reinforced Masonry Frame | 4/13/2021 | Approved | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | DANIEL COLLINS |
| Final | 4/20/2021 | OK for TCO | DANIEL COLLINS |
| Pre-Inspection | 4/26/2021 | Approved | DANIEL COLLINS |
| Final | 5/18/2021 | Conditional Approval | DANIEL COLLINS |