140 N HOOVER ST 90004

Certificate Information: 140 N HOOVER ST 90004

Application / Permit
18016-10000-18357
Plan Check / Job No.
B18LA11499
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL (1) MOMENT FRAME & (3)CANTILEVER COLUMNS
Permit Issued
Issued on 3/11/2020
Issuing Office
Metro
Current Status
CofC Issued on 7/19/2022

Permit Application Status History

Submitted 6/13/2018 APPLICANT
Assigned to Plan Check Engineer 7/25/2018 SAMUEL GONZALEZ
Corrections Issued 7/30/2018 SAMUEL GONZALEZ
Quality Review Completed 8/3/2018 SAI KHUM
Building Plans Picked Up 8/29/2018 APPLICANT
Plan Check Approved 8/28/2019 SAMUEL GONZALEZ
Issued 3/11/2020 LADBS
OK for CofC 7/19/2022 MARK FERRARI
CofC Issued 7/19/2022 WINSTON DUNNING

Permit Application Clearance Information

Housing rent stabilization Cleared 2/18/2020 MICHAEL GREGERSON

Contact Information

Contractor Level Up Construction And Engineering; Lic. No.: 1016289-B 4872 TOPANGA CANYON BLVD #365      WOODLAND HILLS, CA 91364
Engineer Farmand, Anthony E; Lic. No.: C62595 4675 MACARTHUR COURT SUITE 800      NEWPORT BEACH, CA 92660

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2020 Corrections Issued MARK FERRARI
Pre-Inspection 6/26/2020 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 1/6/2021 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 1/14/2021 Corrections Issued MARK FERRARI
Structural Steel Frame 1/14/2021 Not Ready for Inspection MARK FERRARI
Wood Frame 1/14/2021 Not Ready for Inspection MARK FERRARI
Deputy Drilled-In Anchors 2/5/2021 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 2/9/2021 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 2/9/2021 Not Ready for Inspection MARK FERRARI
Wood Frame 2/9/2021 Not Ready for Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 2/10/2021 Approved MARK FERRARI
Structural Steel Frame 2/10/2021 Partial Approval MARK FERRARI
Wood Frame 2/10/2021 Not Ready for Inspection MARK FERRARI
Deputy Reinf. Concrete 2/11/2021 Conditional Approval MARK FERRARI
Wood Frame 2/23/2021 Partial Inspection MARK FERRARI
Wood Frame 3/1/2021 Partial Approval MARK FERRARI
Wood Frame 3/4/2021 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 3/23/2021 Partial Approval MARK FERRARI
Structural Steel Frame 5/6/2021 Conditional Approval DARRYL ARNOLD
Wood Frame 5/6/2021 Approved DARRYL ARNOLD
Structural Steel Frame 5/24/2021 Approved JONATHAN QUACH
Interior/Exterior Lathing 8/2/2021 Corrections Issued MARK FERRARI
Final 10/7/2021 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 10/7/2021 SGSOV Approved MARK FERRARI
Smoke Detectors 10/7/2021 Approved MARK FERRARI
Final 11/8/2021 Conditional Approval MARK FERRARI
Final 7/19/2022 OK for CofC MARK FERRARI