2205 W 15TH ST 90006
Certificate Information: 2205 W 15TH ST 90006
- Application / Permit
- 18016-10000-17325
- Plan Check / Job No.
- B18LA10848
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIV. 93
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/26/2023
Permit Application Status History
| Submitted | 5/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2018 | TSE MING HUANG |
| Corrections Issued | 7/18/2018 | TSE MING HUANG |
| Quality Review Completed | 7/19/2018 | SAI KHUM |
| Building Plans Picked Up | 7/20/2018 | APPLICANT |
| Applicant returned to address corrections | 8/17/2018 | TSE MING HUANG |
| Plan Check Approved | 9/27/2018 | TSE MING HUANG |
| Issued | 5/9/2022 | APPLICANT |
| OK for CofC | 1/26/2023 | DARRYL ARNOLD |
| CofC Issued | 1/26/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/18/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Kohs Construction Co Inc; Lic. No.: 634540-B | 1162 4TH AVE #4 LOS ANGELES, CA 90019 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/7/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 7/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 7/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 7/19/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 7/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 7/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 8/1/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/3/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/3/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 8/5/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/16/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/11/2022 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/25/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 12/9/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/9/2022 | Approved | DARRYL ARNOLD |
| Final | 1/26/2023 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | DARRYL ARNOLD |