15015 W PARTHENIA ST 91343

Certificate Information: 15015 W PARTHENIA ST 91343

Application / Permit
18016-10000-16623
Plan Check / Job No.
B18LA10364
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LAMC DIVISION 93. USING 2 OMF & 2 SHEARWALL.
Permit Issued
Issued on 10/14/2020
Issuing Office
Current Status
Issued on 10/14/2020

Permit Application Status History

Submitted 5/24/2018 APPLICANT
Assigned to Plan Check Engineer 7/12/2018 SAMUEL GONZALEZ
Corrections Issued 7/18/2018 SAMUEL GONZALEZ
Quality Review Completed 7/20/2018 SAI KHUM
Building Plans Picked Up 7/26/2018 APPLICANT
Plan Check Approved 8/12/2020 SAMUEL GONZALEZ
Issued 10/14/2020 APPLICANT

Permit Application Clearance Information

Housing rent stabilization Cleared 9/3/2020 PHILLIP MUNGUIA

Contact Information

Contractor Moraga Builders And Design; Lic. No.: 567115-B 8436 BARDWELL AVENUE      PANORAMA, CA 91402
Engineer Kim, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/25/2020 Partial Inspection DANIEL VARNUM
Footing/Foundation/Slab 1/5/2021 Partial Approval DANIEL VARNUM
Wood Frame 1/14/2021 Not Ready for Inspection DANIEL VARNUM
Wood Frame 1/15/2021 No Access for Inspection JEFFREY FULTON
Wood Frame 2/4/2021 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Partial Approval DANIEL VARNUM
Reinforced Concrete Frame 2/9/2021 Not Ready for Inspection DANIEL VARNUM
Structural Steel Frame 2/9/2021 Not Ready for Inspection DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 2/11/2021 Approved DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval DANIEL VARNUM
Reinforced Concrete Frame 2/11/2021 No Access for Inspection DANIEL VARNUM
Structural Steel Frame 2/11/2021 Not Ready for Inspection DANIEL VARNUM
Structural Steel Frame 2/22/2021 Approved DANIEL VARNUM
Interior/Exterior Lathing 3/9/2021 Approved HAMID PISHEHVAR
Final 4/12/2021 Partial Approval DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Approved DANIEL VARNUM
Smoke Detectors 4/12/2021 Approved DANIEL VARNUM