14701 W RAYEN ST 91402
Certificate Information: 14701 W RAYEN ST 91402
- Application / Permit
- 18016-10000-16591
- Plan Check / Job No.
- B18LA10341
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER DIVISION 93. RETROFIT CONSISTS OF INSTALLING (2) STEEL SPECIAL CANTILEVER COLUMNS AND WOOD SHEAR WALLS TO EXISTING 3-STORY APARTMENT BUILDING
- Permit Issued
- Issued on 3/26/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/25/2021
Permit Application Status History
| Submitted | 5/24/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2018 | RICARDO SUPAN |
| Corrections Issued | 7/16/2018 | RICARDO SUPAN |
| Quality Review Completed | 7/16/2018 | SAI KHUM |
| Building Plans Picked Up | 7/17/2018 | APPLICANT |
| Applicant returned to address corrections | 11/13/2018 | RICARDO SUPAN |
| Plan Check Approved | 11/13/2018 | RICARDO SUPAN |
| Issued | 3/26/2020 | LADBS |
| OK for CofC | 1/13/2021 | MARK FERRARI |
| CofC Issued | 1/25/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/19/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Rigid Design & Construction Inc; Lic. No.: 947498-B | 14813 MORRISON ST SHERMAN OAKS, CA 91403 |
| Engineer | Alexander,, Andy Joseph; Lic. No.: C84086 | 1730 E HOLLY AVE STE 107 EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 4/1/2020 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 4/3/2020 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 5/6/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 5/6/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | Partial Approval | HAMID PISHEHVAR |
| Wood Frame | 5/22/2020 | Partial Approval | HAMID PISHEHVAR |
| Deputy Wood Construction | 6/5/2020 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Conditional Approval | DANIEL VARNUM |
| Structural Steel Frame | 6/5/2020 | Conditional Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 6/22/2020 | Approved | DANIEL VARNUM |
| Final | 10/19/2020 | Partial Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 10/19/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 10/19/2020 | Approved | DANIEL VARNUM |
| Final | 1/13/2021 | OK for CofC | MARK FERRARI |