621 W 81ST ST 90044

Certificate Information: 621 W 81ST ST 90044

Application / Permit
18016-10000-15924
Plan Check / Job No.
B18LA09923
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93.INSTALL 3 MOMENT FRAMES.
Permit Issued
Issued on 8/10/2020
Issuing Office
Current Status
CofC Issued on 10/3/2022

Permit Application Status History

Submitted 5/18/2018 APPLICANT
Assigned to Plan Check Engineer 7/5/2018 DANIEL SANJUAN
Corrections Issued 7/11/2018 DANIEL SANJUAN
Quality Review Completed 7/13/2018 SAI KHUM
Building Plans Picked Up 7/17/2018 APPLICANT
Plan Check Approved 9/18/2019 DANIEL SANJUAN
Issued 8/10/2020 APPLICANT
OK for CofC 10/3/2022 WINSTON DUNNING
OK to Issue CofC 10/3/2022 WINSTON DUNNING
CofC Issued 10/3/2022 WINSTON DUNNING

Permit Application Clearance Information

Housing rent stabilization Cleared 6/3/2019 DAN HAECKER

Contact Information

Contractor In Gods Hands Construction Inc; Lic. No.: 977751-B 10936 DAINES DRIVE      TEMPLE CITY, CA 91780
Engineer Coronado, Jeff; Lic. No.: S3927 553 ST MALO ST      WEST COVINA, CA 91790

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/6/2022 Conditional Approval DARRYL ARNOLD
Deputy Other (see comments) 6/22/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 6/22/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 7/21/2022 Conditional Approval DARRYL ARNOLD
Special/Order Compliance 8/4/2022 No Access for Inspection DARRYL ARNOLD
Interior/Exterior Lathing 9/8/2022 Conditional Approval DARRYL ARNOLD
Final 9/16/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 9/16/2022 Corrections Issued DARRYL ARNOLD
Final 9/20/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 9/20/2022 Not Ready for Inspection DARRYL ARNOLD
Final 9/28/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Not Ready DARRYL ARNOLD
Final 9/30/2022 Partial Inspection WINSTON DUNNING
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Approved WINSTON DUNNING
Smoke Detectors 9/30/2022 Approved WINSTON DUNNING
Final 10/3/2022 OK for CofC WINSTON DUNNING