10941 W STRATHMORE DR 90024
Certificate Information: 10941 W STRATHMORE DR 90024
- Application / Permit
- 18016-10000-14890
- Plan Check / Job No.
- B18LA09298
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment Hotel
- Work Description
- SOFT STORY RETROFIT AS PER LAMC DIVISION 93 OF APARTMENT HOTEL. INSTALL (N) OMF.
- Permit Issued
- Issued on 2/26/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/29/2021
Permit Application Status History
| Submitted | 5/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2018 | SAMUEL GONZALEZ |
| Corrections Issued | 6/28/2018 | SAMUEL GONZALEZ |
| Quality Review Completed | 6/29/2018 | SAI KHUM |
| Building Plans Picked Up | 7/23/2018 | APPLICANT |
| Plan Check Approved | 9/10/2019 | SAMUEL GONZALEZ |
| No Progress | 1/27/2020 | VARAND SARKISIAN |
| Plan Check Approved | 2/19/2020 | VARAND SARKISIAN |
| Issued | 2/26/2020 | LADBS |
| OK for CofC | 4/26/2021 | GRANT WOODS |
| CofC Issued | 4/29/2021 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 12/4/2019 | STEVEN HOFSTAD |
| DAS Clearance | Cleared | 2/18/2020 | VARAND SARKISIAN |
Contact Information
| Contractor | Core Contractors Llc; Lic. No.: 1038618-B | 9800D TOPANGA CANYON BLVD SUITE 324 CHATSWORTH, CA 91311 |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: C78194 | 23172 PLAZA POINTE DR STE 145 LAGUNA HILLS, CA 92653 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 6/30/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 6/30/2020 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 7/6/2020 | Conditional Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 7/7/2020 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 7/9/2020 | Corrections Issued | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/9/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Structural Steel Frame | 7/9/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/13/2020 | Approved | PAUL DAVIDSON |
| Structural Steel Frame | 7/13/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Steel/Welding | 7/14/2020 | Conditional Approval | GRANT WOODS |
| Structural Steel Frame | 7/16/2020 | Approved | PAUL DAVIDSON |
| Wood Frame | 7/16/2020 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/20/2020 | Approved | GRANT WOODS |
| Final | 7/28/2020 | Partial Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/28/2020 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 7/28/2020 | Approved | GRANT WOODS |
| Final | 4/26/2021 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 4/26/2021 | SGSOV Approved | GRANT WOODS |