4225 W ADAMS BLVD 90018

Certificate Information: 4225 W ADAMS BLVD 90018

Application / Permit
18016-10000-13258
Plan Check / Job No.
B18LA08279
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LAMC DIV. 93. INSTALL STEEL CANTILEVER COLUMNS
Permit Issued
Issued on 10/15/2020
Issuing Office
Current Status
CofC Issued on 7/28/2021

Permit Application Status History

Submitted 4/27/2018 APPLICANT
Assigned to Plan Check Engineer 5/31/2018 MANUEL MONTUFAR
Corrections Issued 6/4/2018 MANUEL MONTUFAR
Quality Review Completed 6/7/2018 SAI KHUM
Building Plans Picked Up 6/20/2018 APPLICANT
Plan Check Approved 10/2/2018 MANUEL MONTUFAR
Issued 10/15/2020 APPLICANT
OK for CofC 6/9/2021 DARRYL ARNOLD
CofC Issued 7/28/2021 WINSTON DUNNING

Permit Application Clearance Information

HPOZ Cleared 7/26/2018 MAX LODER
Housing rent stabilization Cleared 9/28/2020 PHILLIP MUNGUIA

Contact Information

Contractor Omega Structural Inc; Lic. No.: 998075-B 4269 S HARVARD BOULEVARD      LOS ANGELES, CA 90062
Engineer , ; Lic. No.: C84000       ,

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2021 Conditional Approval DARRYL ARNOLD
Deputy Other (see comments) 3/15/2021 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 3/19/2021 Approved DARRYL ARNOLD
Footing/Foundation/Slab 3/19/2021 Approved DARRYL ARNOLD
Wood Frame 3/31/2021 Approved DARRYL ARNOLD
Deputy Wood Construction 4/14/2021 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 4/15/2021 Conditional Approval DARRYL ARNOLD
Wood Frame 4/15/2021 Approved DARRYL ARNOLD
Interior/Exterior Lathing 4/20/2021 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 5/26/2021 Approved DARRYL ARNOLD
Final 6/7/2021 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 6/7/2021 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 6/7/2021 SGSOV Not Ready DARRYL ARNOLD
Final 6/9/2021 OK for CofC DARRYL ARNOLD
METHANE-Final 6/9/2021 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 6/9/2021 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 6/9/2021 Approved DARRYL ARNOLD