12530 W CLOUD LANE 90049

Certificate Information: 12530 W CLOUD LANE 90049

Application / Permit
18016-10000-13056
Plan Check / Job No.
B18LA08160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel to (e) single family dwelling with attached garage at bedrooms, kitchen, dining room, bathrooms. Raise roof height at bedroom and dining room
Permit Issued
Issued on 8/21/2018
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 5/26/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/26/2018 APPLICANT
Assigned to Plan Check Engineer 5/17/2018 VU NGUYEN
Corrections Issued 5/22/2018 VU NGUYEN
Quality Review Completed 5/24/2018 DAVID CHANG
Building Plans Picked Up 6/11/2018 APPLICANT
Green Plans Picked Up 6/11/2018 APPLICANT
Plan Check Approved 8/16/2018 VU NGUYEN
Issued 8/21/2018 LADBS
Permit Finaled-Status Void 5/15/2026 KEVIN SARGSYAN
Re-Activate Permit 5/22/2026 KEVIN SARGSYAN
Permit Finaled 5/26/2026 KEVIN SARGSYAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/24/2018 NAZILA NOORIFAR
Green Code Cleared 7/24/2018 SARAH ABOULHOSN
Roof/Waste drainage to street Cleared 7/24/2018 NAZILA NOORIFAR
Sewer availability Cleared 7/24/2018 NAZILA NOORIFAR
Grading Pre-Inspection Cleared 8/16/2018 VU NGUYEN

Contact Information

Architect Schmidt, James Warren Jr; Lic. No.: C22142 4380 IRVINE AVENUE      STUDIO CITY, CA 91604
Contractor Shramek Building Company; Lic. No.: 492534-B 6032 JASONWOOD DRIVE      HUNTINGTON BEACH, CA 92648
Engineer Mallak, Nabil Michel; Lic. No.: S5351 6385 GREEN VALLEY CIR 218      CULVER CITY, CA 90230
Geologist Daugherty, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 12/27/2018 Approved KENNETH NAGLE
PLUMBING-Rough 1/30/2019 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 3/22/2019 Corrections Issued KENNETH NAGLE
Footing/Foundation/Slab 3/29/2019 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 4/17/2019 Approved KENNETH NAGLE
BUILDING-Rough-Frame 2/25/2020 Corrections Issued TIM CHRISTENSEN
PLUMBING-Rough 1/11/2021 Partial Approval PIERRE VEGA
HVAC-Rough 3/1/2021 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 5/7/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/14/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 5/14/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 5/18/2021 Approved JUAN VALENZUELA
HVAC-Rough 5/18/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 5/18/2021 Approved JUAN VALENZUELA
Insulation 5/20/2021 Approved JUAN VALENZUELA
Drywall Nailing 5/27/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/10/2021 Not Ready for Inspection AMY COLIN
Shower Pan 6/10/2021 Approved AMY COLIN
Interior/Exterior Lathing 6/21/2021 Partial Approval ADAM ESCOTO
HVAC-Final 3/15/2022 Corrections Issued ANDREW NAVE
Special/Order Compliance 3/15/2022 Partial Inspection PATRICK QUALEY
HVAC-Final 5/6/2022 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 7/14/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 7/26/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 8/19/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 9/11/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 9/11/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/11/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 9/11/2023 Approved ARAM AVEDISIAN
Final 10/16/2023 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Not Ready KEVIN SARGSYAN
ELECTRICAL-Final 1/12/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 1/22/2024 Approved HERBERT GIRON
Final 3/6/2024 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/6/2024 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/6/2024 SGSOV Not Ready KEVIN SARGSYAN
HVAC-Final 3/8/2024 Approved ARAM AVEDISIAN
Final 4/16/2024 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 4/16/2024 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Not Ready CHRISTOPHER WILSON
Service/Power Release 4/16/2024 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 6/4/2024 Partial Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 7/12/2024 Approved KEVIN SARGSYAN
Deputy Grading 11/12/2024 Conditional Approval KEVIN SARGSYAN
Deputy Grading 11/13/2024 Conditional Approval KEVIN SARGSYAN
Deputy Grading 11/14/2024 Conditional Approval KEVIN SARGSYAN
Deputy Grading 11/15/2024 Conditional Approval KEVIN SARGSYAN
Deputy Grading 11/18/2024 Conditional Approval KEVIN SARGSYAN
Deputy Grading 11/19/2024 Conditional Approval KEVIN SARGSYAN
Deputy Grading 11/21/2024 Conditional Approval KEVIN SARGSYAN
Deputy Grading 11/22/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/12/2025 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 5/12/2025 Partial Approval KEVIN SARGSYAN
Final 1/29/2026 No Access for Inspection KEVIN SARGSYAN
Final 5/15/2026 Partial Approval KEVIN SARGSYAN