5429 N NEWCASTLE AVE 91316
Certificate Information: 5429 N NEWCASTLE AVE 91316
- Application / Permit
- 18016-10000-12826
- Plan Check / Job No.
- B18LA08015
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- SOFT STORY RETROFIT PER LAMC Division 93. INSTALL 6 (N) SPECIAL CANTILEVER COLUMN
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- CofC Issued on 10/7/2021
Permit Application Status History
| Submitted | 4/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2018 | VARAND SARKISIAN |
| Corrections Issued | 5/29/2018 | VARAND SARKISIAN |
| Quality Review Completed | 6/4/2018 | CELESTE MORRIS |
| Building Plans Picked Up | 6/5/2018 | APPLICANT |
| Plan Check Approved | 8/3/2020 | VARAND SARKISIAN |
| Issued | 8/5/2020 | APPLICANT |
| OK for CofC | 7/7/2021 | KENNETH ROBERTS |
| CofC Issued | 10/7/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/23/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/10/2020 | Partial Inspection | DANIEL VARNUM |
| Deputy Steel/Welding | 8/17/2020 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 8/20/2020 | Approved | DANIEL VARNUM |
| Deputy Steel/Welding | 9/4/2020 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 9/18/2020 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 9/22/2020 | Conditional Approval | DANIEL VARNUM |
| Structural Steel Frame | 9/28/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 9/28/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 10/8/2020 | Corrections Issued | DANIEL VARNUM |
| Structural Steel Frame | 10/14/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 10/20/2020 | Approved | DANIEL VARNUM |
| Final | 1/13/2021 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 1/13/2021 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 1/13/2021 | Approved | DANIEL VARNUM |
| Final | 3/12/2021 | Partial Approval | DANIEL VARNUM |
| Final | 7/7/2021 | OK for CofC | KENNETH ROBERTS |