1666 W 2ND ST 90026
Certificate Information: 1666 W 2ND ST 90026
- Application / Permit
- 18016-10000-12772
- Plan Check / Job No.
- B18LA07976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC DIV. 93 USING SCCS.
- Permit Issued
- Issued on 7/24/2020
- Issuing Office
- Current Status
- CofC Issued on 12/9/2020
Permit Application Status History
| Submitted | 4/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2018 | JAIME OROZCO |
| Corrections Issued | 5/13/2018 | JAIME OROZCO |
| Quality Review Completed | 5/16/2018 | SAI KHUM |
| Building Plans Picked Up | 5/24/2018 | APPLICANT |
| Plan Check Approved | 6/7/2018 | JAIME OROZCO |
| No Progress | 6/7/2018 | JAIME OROZCO |
| Plan Check Approved | 6/29/2020 | JAIME OROZCO |
| Issued | 7/24/2020 | APPLICANT |
| OK for CofC | 12/7/2020 | MARK FERRARI |
| CofC Issued | 12/9/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 11/21/2018 | JIM URQUHART |
| Abandoned oil well approval | Cleared | 12/20/2018 | ROBERT DUFF |
| Abandoned oil well | Cleared | 1/16/2020 | ROBERT DUFF |
| Housing rent stabilization | Cleared | 7/22/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Youhanna, T Labib; Lic. No.: S4549 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2020 | Corrections Issued | MARK FERRARI |
| Deputy Drilled-In Anchors | 9/9/2020 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 9/9/2020 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 9/9/2020 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 9/9/2020 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 9/11/2020 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 9/18/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 9/25/2020 | Approved | MARK FERRARI |
| Wood Frame | 9/25/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 11/16/2020 | Corrections Issued | MARK FERRARI |
| Final | 12/1/2020 | Corrections Issued | MARK FERRARI |
| METHANE-Final | 12/1/2020 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 12/1/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 12/1/2020 | Approved | MARK FERRARI |
| Final | 12/4/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 12/7/2020 | OK for CofC | MARK FERRARI |