8730 N PARTHENIA PL 91343
Certificate Information: 8730 N PARTHENIA PL 91343
- Application / Permit
- 18016-10000-11115
- Plan Check / Job No.
- B18LA06965
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LAMC DIVISON 93. INSTALL (N) SHEAR WALLS AND (N) MOMENT FRAMES
- Permit Issued
- Issued on 4/16/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/14/2023
Permit Application Status History
| Submitted | 4/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2018 | MANUEL MONTUFAR |
| Corrections Issued | 4/23/2018 | MANUEL MONTUFAR |
| Quality Review Completed | 4/23/2018 | SAI KHUM |
| Building Plans Picked Up | 4/25/2018 | APPLICANT |
| Plan Check Approved | 5/15/2018 | MANUEL MONTUFAR |
| Issued | 4/16/2020 | LADBS |
| OK for CofC | 2/14/2023 | RICKEY JACKSON |
| CofC Issued | 2/14/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/6/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Weinstein Construction Corporation; Lic. No.: 630439-B | 15102 RAYMER STREET VAN NUYS, CA 91405 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/7/2020 | Partial Inspection | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 5/21/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 5/21/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 5/21/2020 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 5/22/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 6/2/2020 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2020 | Approved | DANIEL VARNUM |
| Insulation | 6/5/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 6/17/2020 | Approved | DANIEL VARNUM |
| Final | 8/18/2020 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 8/18/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 8/18/2020 | Approved | DANIEL VARNUM |
| Special/Order Compliance | 10/20/2021 | No Access for Inspection | DANIEL VARNUM |
| Final | 2/14/2023 | OK for CofC | RICKEY JACKSON |