1661 W 259TH ST 90710
Certificate Information: 1661 W 259TH ST 90710
- Application / Permit
- 18016-10000-10598
- Plan Check / Job No.
- B18LA06703
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL (N) CANTILEVER COLUMNS AT THE TUCK UNDER PARKING REGIONS OF A 2 STORY APARTMENT BLDG.
- Permit Issued
- Issued on 6/2/2020
- Issuing Office
- Current Status
- CofC Issued on 12/30/2021
Permit Application Status History
| Submitted | 4/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2018 | HANS SANTIAGO |
| Corrections Issued | 5/8/2018 | HANS SANTIAGO |
| Re-Submittal Required | 5/10/2018 | SAI KHUM |
| Building Plans Picked Up | 5/17/2018 | APPLICANT |
| Re-Submitted | 8/30/2018 | HANS SANTIAGO |
| Corrections Issued 2 | 2/19/2019 | HANS SANTIAGO |
| Submitted for Second Quality Review | 2/19/2019 | HANS SANTIAGO |
| Plan Check Approved | 2/19/2019 | Andrew Santiago |
| Issued | 6/2/2020 | APPLICANT |
| OK for CofC | 12/27/2021 | NICK LAROCCA |
| CofC Issued | 12/30/2021 | NICK LAROCCA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2019 | JEANETTE VONG |
| Encroachment in public way | Cleared | 1/29/2019 | KARAN PATEL |
| Work Adjacent to Public Way | Cleared | 1/29/2019 | CHIU TAM |
| Housing rent stabilization | Cleared | 6/1/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Global Builders Inc; Lic. No.: 1045058-B | 1740 E GARRY AVENUE SANTA ANA, CA 92705 |
| Engineer | Iwekaogwu, Francis Egbule; Lic. No.: C53339 | 6372 CHIPOLA CT CHINO, CA 91710 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 1/8/2021 | Partial Approval | JOEY BUCHANAN |
| Deputy Other (see comments) | 1/20/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 1/20/2021 | Partial Approval | JOEY BUCHANAN |
| Structural Steel Frame | 2/12/2021 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 2/12/2021 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 2/19/2021 | Partial Approval | JOEY BUCHANAN |
| Structural Steel Frame | 2/19/2021 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 2/22/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/1/2021 | Partial Approval | NICK LAROCCA |
| Wood Frame | 4/29/2021 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 5/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 5/21/2021 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 5/21/2021 | Partial Approval | NICK LAROCCA |
| Interior/Exterior Lathing | 6/25/2021 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 12/21/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 12/21/2021 | Approved | JOEY BUCHANAN |
| Final | 12/27/2021 | OK for CofC | NICK LAROCCA |
| METHANE-Final | 12/27/2021 | Approved | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Approved | NICK LAROCCA |
| Smoke Detectors | 12/27/2021 | Approved | NICK LAROCCA |