8641 N WILLIS AVE 91402

Certificate Information: 8641 N WILLIS AVE 91402

Application / Permit
18016-10000-10318
Plan Check / Job No.
B18LA06523
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LAMC DIVISION 93. INSTALL STEEL MOMENT FRAMES.
Permit Issued
Issued on 2/19/2020
Issuing Office
Metro
Current Status
CofC Issued on 4/13/2021

Permit Application Status History

Submitted 4/5/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 MANUEL MONTUFAR
Corrections Issued 4/18/2018 MANUEL MONTUFAR
Quality Review Completed 4/19/2018 SAI KHUM
Building Plans Picked Up 4/24/2018 APPLICANT
Plan Check Approved 5/24/2018 MANUEL MONTUFAR
Issued 2/19/2020 LADBS
OK for CofC 4/13/2021 JEFFREY DURAN
CofC Issued 4/13/2021 JEFFREY DURAN

Permit Application Clearance Information

Housing rent stabilization Cleared 1/31/2020 MICHAEL GREGERSON

Contact Information

Contractor Ace Construction Inc; Lic. No.: 809243-B 11921 SHERMAN WAY      NORTH HOLLYWOOD, CA 91605
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/26/2020 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 6/15/2020 Conditional Approval VAHE KELEDJIAN
Deputy Steel/Welding 6/15/2020 Conditional Approval VAHE KELEDJIAN
Footing/Foundation/Slab 9/9/2020 Approved DANIEL VARNUM
Structural Steel Frame 9/9/2020 Approved DANIEL VARNUM
Wood Frame 9/9/2020 Approved DANIEL VARNUM
Interior/Exterior Lathing 12/1/2020 Approved DANIEL VARNUM
Final 1/28/2021 Partial Approval DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 1/28/2021 SGSOV Approved DANIEL VARNUM
Smoke Detectors 1/28/2021 Approved DANIEL VARNUM
Final 4/13/2021 OK for CofC JEFFREY DURAN