960 N LA BREA AVE 90038

Certificate Information: 960 N LA BREA AVE 90038

Application / Permit
18016-10000-09955
Plan Check / Job No.
B18LA06301
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Gymnasium
Work Description
Conversion of existing 5-story NDC warehouse bldg to commercial (Fitness Center) . Existing attached parking structure to remain as parking use and a portion converted to commercial (Fitness Center). Permit for structural and core and shell.
Permit Issued
Issued on 7/3/2019
Issuing Office
Metro
Current Status
Permit Finaled on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2018 APPLICANT
Disabled Access Plans Picked Up 4/13/2018 APPLICANT
Green Plans Picked Up 4/23/2018 APPLICANT
Assigned to Plan Check Engineer 5/3/2018 SUEN LIEU
Corrections Issued 5/17/2018 SUEN LIEU
Quality Review Completed 5/22/2018 CHARLES CHANG
Building Plans Picked Up 5/22/2018 APPLICANT
Applicant returned to address corrections 5/30/2018 SUEN LIEU
Applicant returned to address corrections 6/8/2018 SUEN LIEU
Applicant returned to address corrections 6/13/2018 SUEN LIEU
Applicant returned to address corrections 6/18/2018 SUEN LIEU
Applicant returned to address corrections 6/21/2018 SUEN LIEU
Applicant returned to address corrections 6/22/2018 SUEN LIEU
Applicant returned to address corrections 6/29/2018 SUEN LIEU
Applicant returned to address corrections 7/10/2018 SUEN LIEU
Applicant returned to address corrections 7/12/2018 SUEN LIEU
Applicant returned to address corrections 7/17/2018 SUEN LIEU
Refund Closed 8/16/2018 CHRISTINA TABIRARA
Reactivate - Status Void 8/16/2018 CHRISTINA TABIRARA
Applicant returned to address corrections 10/25/2018 SUEN LIEU
Applicant returned to address corrections 11/16/2018 SUEN LIEU
Applicant returned to address corrections 11/30/2018 SUEN LIEU
Applicant returned to address corrections 2/26/2019 SUEN LIEU
Applicant returned to address corrections 3/8/2019 SUEN LIEU
Applicant returned to address corrections 3/11/2019 SUEN LIEU
Applicant returned to address corrections 3/15/2019 SUEN LIEU
Applicant returned to address corrections 3/20/2019 SUEN LIEU
Applicant returned to address corrections 3/22/2019 SUEN LIEU
Applicant returned to address corrections 3/26/2019 SUEN LIEU
Applicant returned to address corrections 4/3/2019 SUEN LIEU
Applicant returned to address corrections 5/10/2019 SUEN LIEU
Applicant returned to address corrections 6/11/2019 SUEN LIEU
Applicant returned to address corrections 6/21/2019 SUEN LIEU
Applicant returned to address corrections 6/27/2019 SUEN LIEU
Applicant returned to address corrections 6/28/2019 SUEN LIEU
Plan Check Approved 7/2/2019 SUEN LIEU
Issued 7/3/2019 LADBS
Refund in Progress-Status Void 8/15/2019 EMILY HU
Re-Activate Permit 8/21/2019 MARY SUM
Refund Completed-Status Void 11/14/2019 CHRISTINA TABIRARA
Re-Activate Permit 11/21/2019 MARY SUM
Permit Finaled 11/18/2022 TIMOTHY BUXTON

Permit Application Clearance Information

DAS Clearance Cleared 7/26/2018 SHINE LIN
ZA Case Cleared 4/19/2019 ANNA VAN
ZA Case Cleared 4/19/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 5/10/2019 ERIK BEASLEY
Green Code Cleared 5/16/2019 KHEDER ALRAZAA
Hydrant and Access approval Cleared 5/16/2019 JOHN CONNEALLY
Sewer availability Cleared 5/16/2019 CELINA MORENO
Fire Marshall Fire Life Safety Cleared 6/4/2019 VIDAL GARCIA
"Q" conditions Cleared 6/5/2019 SOPHIE GABEL-SCHEINBAU
"T" removal Cleared 6/5/2019 SOPHIE GABEL-SCHEINBAU
CPC Cleared 6/5/2019 SOPHIE GABEL-SCHEINBAU
Excavation more than 5-ft deep Cleared 6/11/2019 CALOSHA APPROVED
Low Impact Development Cleared 6/11/2019 SEAN SHAHMIRI
Roof/Waste drainage to street Cleared 6/11/2019 CELINA MORENO
Stormwater Pollution Mitigatn Cleared 6/11/2019 SEAN SHAHMIRI
Work Adjacent to Public Way Cleared 6/11/2019 BOK GOH
Food Service Establishment Cleared 6/21/2019 RAMESHBHAIR PATEL
Food establishment approval Cleared 7/2/2019 LACDHS APPROVED

Contact Information

Architect Vanmali,, Ashokkumar; Lic. No.: C26014 GRUEN ASSOCIATES   6330 SAN VICENTE BLVD. STE. 200    LOS ANGELES, CA 90048
Contractor Ferrante Koberling Construction Inc; Lic. No.: 988562-B 4700 W JEFFERSON BLVD #103      LOS ANGELES, CA 90016
Engineer Harris,, James Edward; Lic. No.: GE2100 3072 BURNEY PLACE      LOS ALAMITOS, CA 90720
Engineer Yu, Philip Junior Davi; Lic. No.: S5854 3828 EARLE AVE      ROSEMEAD, CA 91770
Landscape Architect Howell,, Dean Edward; Lic. No.: LA5765 851 N OGDEN DR      LOS ANGELES, CA 90046

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/2/2019 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 8/9/2019 Approved DAVID BURKHEAD
Reinforced Concrete Frame 8/9/2019 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 8/12/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/16/2019 Partial Approval DAVID BURKHEAD
Deputy Shotcrete 8/23/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/3/2019 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/5/2019 Corrections Issued DAVID BURKHEAD
Deputy Shotcrete 9/9/2019 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/9/2019 Partial Approval DAVID BURKHEAD
Deputy Shotcrete 9/11/2019 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 9/12/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/19/2019 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 9/20/2019 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 9/20/2019 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 9/23/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/23/2019 Partial Approval DAVID BURKHEAD
Deputy Shotcrete 9/24/2019 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 9/26/2019 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 9/27/2019 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/18/2019 Partial Inspection GRANT WOODS
Footing/Foundation/Slab 10/25/2019 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/29/2019 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 11/25/2019 Not Ready for Inspection JONATHAN QUACH
Green Building Rough 11/25/2019 Not Ready for Inspection JONATHAN QUACH
Reinforced Concrete Frame 11/25/2019 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Concrete 11/27/2019 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 11/27/2019 Partial Approval JONATHAN QUACH
Deputy Methane Barrier 12/3/2019 Conditional Approval KATY RAMIREZ
METHANE-Rough 12/3/2019 Not Ready for Inspection KATY RAMIREZ
Deputy Methane Barrier 12/4/2019 Conditional Approval TIMOTHY BUXTON
Deputy Methane Barrier 12/5/2019 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 12/6/2019 Conditional Approval TIMOTHY BUXTON
Deputy Methane Barrier 12/9/2019 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 12/10/2019 Partial Approval JONATHAN QUACH
Green Building Rough 12/10/2019 Not Ready for Inspection JONATHAN QUACH
METHANE-Rough 12/10/2019 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 12/10/2019 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 12/10/2019 Not Ready for Inspection JONATHAN QUACH
Deputy Methane Barrier 12/12/2019 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 12/12/2019 Partial Approval JONATHAN QUACH
Green Building Rough 12/12/2019 Not Ready for Inspection JONATHAN QUACH
METHANE-Rough 12/12/2019 Not Ready for Inspection JONATHAN QUACH
Structural Steel Frame 12/12/2019 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 1/16/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 1/16/2020 Partial Approval EDWIN GREGORYONA
Pre-Inspection 2/24/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Methane Barrier 2/28/2020 Conditional Approval JONATHAN QUACH
Pre-Inspection 2/28/2020 Not Ready for Inspection JONATHAN QUACH
Deputy Methane Barrier 3/2/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 3/3/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 3/4/2020 Conditional Approval JONATHAN QUACH
Green Building Rough 3/4/2020 Not Ready for Inspection JONATHAN QUACH
METHANE-Rough 3/4/2020 Not Ready for Inspection JONATHAN QUACH
Reinforced Concrete Frame 3/4/2020 Partial Approval JONATHAN QUACH
Structural Steel Frame 3/4/2020 Not Ready for Inspection JONATHAN QUACH
Deputy Methane Barrier 3/5/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 3/9/2020 Conditional Approval TIMOTHY BUXTON
Deputy Methane Barrier 3/10/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 3/10/2020 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 3/17/2020 Conditional Approval JONATHAN QUACH
Deputy Fireproofing 3/17/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 3/17/2020 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 3/18/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 3/18/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 4/6/2020 Conditional Approval TIMOTHY BUXTON
Deputy Methane Barrier 4/7/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 4/8/2020 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 4/9/2020 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 4/9/2020 Conditional Approval TIMOTHY BUXTON
Deputy Methane Barrier 4/14/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 4/15/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 4/16/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 4/21/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 4/22/2020 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 5/4/2020 Partial Approval JONATHAN QUACH
Footing/Foundation/Slab 5/5/2020 Partial Approval JONATHAN QUACH
Footing/Foundation/Slab 5/12/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 5/27/2020 Partial Approval TIMOTHY BUXTON
Deputy Methane Barrier 6/4/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 6/5/2020 Conditional Approval JONATHAN QUACH
METHANE-Rough 6/8/2020 Approved JONATHAN QUACH
Light Gage Steel Frame 6/11/2020 Partial Inspection JONATHAN QUACH
Footing/Foundation/Slab 6/15/2020 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 6/17/2020 Not Ready for Inspection JONATHAN QUACH
Deputy Methane Barrier 6/18/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 6/19/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 6/26/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 7/14/2020 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 8/21/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 8/21/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 9/2/2020 Partial Approval TIMOTHY BUXTON
Green Building Rough 9/2/2020 Not Ready for Inspection TIMOTHY BUXTON
Drywall Nailing 9/3/2020 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 9/11/2020 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Approved TIMOTHY BUXTON
Green Building Rough 11/19/2020 Approved TIMOTHY BUXTON
Light Gage Steel Frame 11/19/2020 Partial Approval TIMOTHY BUXTON
Structural Steel Frame 11/19/2020 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 11/25/2020 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 12/3/2020 Partial Approval TIMOTHY BUXTON
Drywall Nailing 1/12/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 1/20/2021 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 1/25/2021 Partial Approval TIMOTHY BUXTON
Reinforced Concrete Frame 2/8/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 2/22/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 2/22/2021 Not Ready for Inspection TIMOTHY BUXTON
Drywall Nailing 3/12/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 3/12/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 3/23/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 3/23/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 3/30/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 4/8/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 4/16/2021 Not Ready for Inspection TIMOTHY BUXTON
Light Gage Steel Frame 4/16/2021 Partial Approval TIMOTHY BUXTON
T-Bar Ceiling 4/16/2021 Not Ready for Inspection TIMOTHY BUXTON
Light Gage Steel Frame 4/30/2021 Approved TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 5/18/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 5/21/2021 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/21/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/2/2021 Partial Approval TIMOTHY BUXTON
Interior/Exterior Lathing 6/2/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 6/21/2021 Not Ready for Inspection JONATHAN QUACH
Light Gage Steel Frame 6/21/2021 Not Ready for Inspection JONATHAN QUACH
T-Bar Ceiling 6/21/2021 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 6/23/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 6/23/2021 Partial Approval TIMOTHY BUXTON
T-Bar Ceiling 6/23/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 7/1/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 7/21/2021 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/21/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/6/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 8/12/2021 Partial Approval TIMOTHY BUXTON
Insulation 8/12/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 8/12/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 8/18/2021 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 9/10/2021 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 9/13/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 9/15/2021 Conditional Approval TIMOTHY BUXTON
Drywall Nailing 9/22/2021 Partial Approval TIMOTHY BUXTON
Wood Frame 9/22/2021 Partial Approval TIMOTHY BUXTON
Insulation 9/29/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 10/7/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 10/7/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 10/13/2021 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 10/13/2021 Partial Approval JONATHAN QUACH
Interior/Exterior Lathing 10/14/2021 Partial Approval JONATHAN QUACH
T-Bar Ceiling 11/1/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 11/18/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 11/29/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 1/3/2022 Conditional Approval DARRYL ARNOLD
Pre-Inspection 2/11/2022 Approved TIMOTHY BUXTON
Light Gage Steel Frame 2/17/2022 Partial Approval TIMOTHY BUXTON
Pre-Inspection 2/28/2022 Approved TIMOTHY BUXTON
Drywall Nailing 3/24/2022 Partial Approval TED RIES
Structural Steel Frame 4/11/2022 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 4/25/2022 Approved TIMOTHY BUXTON
Light Gage Steel Frame 5/3/2022 Approved TIMOTHY BUXTON
Light Gage Steel Frame 5/9/2022 Approved TIMOTHY BUXTON
Special/Order Compliance 5/9/2022 Approved TIMOTHY BUXTON
Final 5/24/2022 Partial Inspection TIMOTHY BUXTON
Drywall Nailing 6/3/2022 Approved TIMOTHY BUXTON
Final 6/3/2022 Conditional Approval TIMOTHY BUXTON
Green Building Final 6/3/2022 Approved TIMOTHY BUXTON
Reinforced Concrete Frame 6/3/2022 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Approved TIMOTHY BUXTON
Smoke Detectors 6/3/2022 Approved TIMOTHY BUXTON
Structural Steel Frame 6/3/2022 Approved TIMOTHY BUXTON
Special/Order Compliance 6/6/2022 Approved TIMOTHY BUXTON