5667 W FOUNTAIN AVE 90028
Certificate Information: 5667 W FOUNTAIN AVE 90028
- Application / Permit
- 18016-10000-08867
- Plan Check / Job No.
- B18LA05658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC DIVISION 93 USING SPECIAL STEEL CANTILEVERED COLUMNS AND WOOD SHEAR WALLS AT THE TUCK UNDER PARKING REGION OF A 2 STORY APARTMENT BLDG.
- Permit Issued
- Issued on 2/26/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 5/14/2021
Permit Application Status History
| Submitted | 3/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2018 | HANS SANTIAGO |
| Corrections Issued | 5/3/2018 | HANS SANTIAGO |
| Quality Review Completed | 5/4/2018 | SAI KHUM |
| Building Plans Picked Up | 5/10/2018 | APPLICANT |
| Applicant returned to address corrections | 5/22/2018 | HANS SANTIAGO |
| Plan Check Approved | 6/1/2018 | Andrew Santiago |
| Issued | 2/26/2020 | LADBS |
| OK for CofC | 4/30/2021 | JONATHAN QUACH |
| CofC Issued | 5/14/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 5/24/2018 | JIM URQUHART |
| Housing rent stabilization | Cleared | 7/29/2019 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | R C R Construction; Lic. No.: 922163-B | 2681 GROVE AVE CORONA, CA 92882 |
| Engineer | , ; Lic. No.: S5339 | 11254 HANNUM AVE CULVER CITY, CA 90230 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 7/13/2020 | Conditional Approval | MARK FERRARI |
| Pre-Inspection | 7/22/2020 | No Access for Inspection | MARK FERRARI |
| Pre-Inspection | 7/24/2020 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 8/7/2020 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 8/7/2020 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 8/7/2020 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 11/6/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 11/6/2020 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 11/17/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Wood Construction | 12/1/2020 | Conditional Approval | FRED WOHLFARTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Approved | JONATHAN QUACH |
| Wood Frame | 12/18/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2020 | Approved | JONATHAN QUACH |
| Wood Frame | 12/22/2020 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 12/30/2020 | Approved | JONATHAN QUACH |
| Final | 1/20/2021 | Not Ready for Inspection | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/20/2021 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 1/20/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 4/30/2021 | OK for CofC | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 4/30/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 4/30/2021 | Approved | JONATHAN QUACH |