15215 W RAYEN ST 91343
Certificate Information: 15215 W RAYEN ST 91343
- Application / Permit
- 18016-10000-07900
- Plan Check / Job No.
- B18LA04981
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIVISION 93. RETROFIT CONSISTS OF INSTALLING (2) NEW ORDINARY MOMENT FRAMES TO EXISTING 2-STORY APARTMENT BUILDING
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 3/16/2021
Permit Application Status History
| Submitted | 3/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2018 | ERIC WONG |
| Corrections Issued | 3/28/2018 | ERIC WONG |
| Quality Review Completed | 3/30/2018 | SAI KHUM |
| Building Plans Picked Up | 4/5/2018 | APPLICANT |
| Plan Check Approved | 4/10/2018 | ERIC WONG |
| Issued | 3/4/2020 | LADBS |
| OK for CofC | 3/10/2021 | MARK FERRARI |
| CofC Issued | 3/16/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/24/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Ace Construction Inc; Lic. No.: 809243-B | 11921 SHERMAN WAY NORTH HOLLYWOOD, CA 91605 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/2/2020 | Partial Inspection | DANIEL VARNUM |
| Special/Order Compliance | 6/3/2020 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 8/12/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 8/12/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 8/12/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 10/1/2020 | Approved | DANIEL VARNUM |
| Final | 10/7/2020 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 10/7/2020 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 10/7/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 10/16/2020 | Partial Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 10/16/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 10/16/2020 | Approved | DANIEL VARNUM |
| Final | 3/10/2021 | OK for CofC | MARK FERRARI |