1720 S 5TH AVE 90019

Certificate Information: 1720 S 5TH AVE 90019

Application / Permit
18016-10000-07836
Plan Check / Job No.
B18LA04947
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LAMC DIV 93 USING MOMENT FRAME AND WOOD SHEAR WALLS OF THE TUCK-UNDER PARKING REGION OF A 2 STORY APARTMENT BLDG.
Permit Issued
Issued on 2/6/2020
Issuing Office
Metro
Current Status
CofC Issued on 7/28/2020

Permit Application Status History

Submitted 3/14/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 HANS SANTIAGO
Corrections Issued 4/9/2018 HANS SANTIAGO
Quality Review Completed 4/10/2018 SAI KHUM
Applicant returned to address corrections 8/10/2018 HANS SANTIAGO
Plan Check Approved 8/21/2018 Andrew Santiago
Issued 2/6/2020 LADBS
OK for CofC 3/25/2020 DARRYL ARNOLD
CofC Issued 7/28/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 1/13/2020 CHARLES GARCIA

Contact Information

Architect , ; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Sinai Construction; Lic. No.: 1035535-B 4489 W PICO BLVD      LOS ANGELES, CA 90019

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/20/2020 Approved DARRYL ARNOLD
Deputy Other (see comments) 3/4/2020 Approved DARRYL ARNOLD
Deputy Wood Construction 3/5/2020 Partial Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 3/6/2020 Approved DARRYL ARNOLD
Footing/Foundation/Slab 3/6/2020 Approved DARRYL ARNOLD
Structural Steel Frame 3/6/2020 Approved DARRYL ARNOLD
Wall Anchors 3/6/2020 Not Ready for Inspection DARRYL ARNOLD
Deputy Reinf. Concrete 3/9/2020 Approved DARRYL ARNOLD
Deputy Wood Construction 3/10/2020 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 3/10/2020 Approved DARRYL ARNOLD
Wood Frame 3/10/2020 Approved DARRYL ARNOLD
Deputy Wood Construction 3/11/2020 Conditional Approval MARK FERRARI
Deputy Wood Construction 3/12/2020 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 3/12/2020 Approved DARRYL ARNOLD
Wood Frame 3/12/2020 Approved DARRYL ARNOLD
Deputy Wood Construction 3/13/2020 Partial Approval DARRYL ARNOLD
Deputy Wood Construction 3/16/2020 Partial Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 3/17/2020 Partial Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Partial Approval DARRYL ARNOLD
Wood Frame 3/17/2020 Partial Approval DARRYL ARNOLD
Deputy Wood Construction 3/18/2020 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 3/18/2020 Approved DARRYL ARNOLD
Interior/Exterior Lathing 3/20/2020 Approved DARRYL ARNOLD
Final 3/25/2020 OK for CofC DARRYL ARNOLD
METHANE-Final 3/25/2020 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/25/2020 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 3/25/2020 Approved DARRYL ARNOLD