1720 S 5TH AVE 90019
Certificate Information: 1720 S 5TH AVE 90019
- Application / Permit
- 18016-10000-07836
- Plan Check / Job No.
- B18LA04947
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIV 93 USING MOMENT FRAME AND WOOD SHEAR WALLS OF THE TUCK-UNDER PARKING REGION OF A 2 STORY APARTMENT BLDG.
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 7/28/2020
Permit Application Status History
| Submitted | 3/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2018 | HANS SANTIAGO |
| Corrections Issued | 4/9/2018 | HANS SANTIAGO |
| Quality Review Completed | 4/10/2018 | SAI KHUM |
| Applicant returned to address corrections | 8/10/2018 | HANS SANTIAGO |
| Plan Check Approved | 8/21/2018 | Andrew Santiago |
| Issued | 2/6/2020 | LADBS |
| OK for CofC | 3/25/2020 | DARRYL ARNOLD |
| CofC Issued | 7/28/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/13/2020 | CHARLES GARCIA |
Contact Information
| Architect | , ; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Sinai Construction; Lic. No.: 1035535-B | 4489 W PICO BLVD LOS ANGELES, CA 90019 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2020 | Approved | DARRYL ARNOLD |
| Deputy Other (see comments) | 3/4/2020 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 3/5/2020 | Partial Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 3/6/2020 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/6/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 3/6/2020 | Approved | DARRYL ARNOLD |
| Wall Anchors | 3/6/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 3/9/2020 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 3/10/2020 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 3/10/2020 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 3/11/2020 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 3/12/2020 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 3/12/2020 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 3/13/2020 | Partial Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 3/16/2020 | Partial Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 3/17/2020 | Partial Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2020 | Partial Approval | DARRYL ARNOLD |
| Wood Frame | 3/17/2020 | Partial Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 3/18/2020 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2020 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/20/2020 | Approved | DARRYL ARNOLD |
| Final | 3/25/2020 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 3/25/2020 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/25/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 3/25/2020 | Approved | DARRYL ARNOLD |