3754 S MOTOR AVE 90034
Certificate Information: 3754 S MOTOR AVE 90034
- Application / Permit
- 18016-10000-05440
- Plan Check / Job No.
- B18LA03364
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Soft story retrofit per LABC CHAPTER 93 for Existing Mixed use Building by using Ordinary Moment Frame
- Permit Issued
- Issued on 4/21/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 7/14/2023
Permit Application Status History
| Submitted | 2/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2018 | DANIEL SANJUAN |
| Corrections Issued | 3/22/2018 | DANIEL SANJUAN |
| Quality Review Completed | 3/23/2018 | SAI KHUM |
| Building Plans Picked Up | 3/27/2018 | APPLICANT |
| Applicant returned to address corrections | 4/27/2018 | DANIEL SANJUAN |
| Plan Check Approved | 5/9/2022 | ANDREW SANTIAGO |
| Issued | 4/21/2023 | APPLICANT |
| OK for CofC | 7/10/2023 | MICHAEL PETRUSKO |
| CofC Issued | 7/14/2023 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 4/5/2022 | SAI KHUM |
| Housing rent stabilization | Cleared | 4/18/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Drilled-In Anchors | 5/19/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Steel/Welding | 5/22/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Reinforced Concrete Frame | 5/23/2023 | Approved | MICHAEL PETRUSKO |
| Structural Steel Frame | 5/23/2023 | Approved | MICHAEL PETRUSKO |
| Structural Steel Frame | 6/9/2023 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 6/9/2023 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 6/20/2023 | Approved | MICHAEL PETRUSKO |
| Interior/Exterior Lathing | 6/20/2023 | Approved | MICHAEL PETRUSKO |
| Final | 7/10/2023 | OK for CofC | MICHAEL PETRUSKO |
| METHANE-Final | 7/10/2023 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 7/10/2023 | Approved | MICHAEL PETRUSKO |