2472 N EASTERN AVE 90032
Certificate Information: 2472 N EASTERN AVE 90032
- Application / Permit
- 18016-10000-04894
- Plan Check / Job No.
- B18LA03028
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIV 93. RETROFIT CONSISTS OF STEEL MOMENT FRAME
- Permit Issued
- Issued on 3/20/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/16/2021
Permit Application Status History
| Submitted | 2/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2018 | ALYSSA N NARCISO |
| Corrections Issued | 3/21/2018 | ALYSSA N NARCISO |
| Quality Review Completed | 3/22/2018 | SAI KHUM |
| Plan Check Approved | 4/11/2019 | ALYSSA N NARCISO |
| Issued | 3/20/2020 | LADBS |
| OK for CofC | 1/22/2021 | MARK FERRARI |
| CofC Issued | 2/16/2021 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/2/2020 | CHARLES GARCIA |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Farmand, Anthony E; Lic. No.: C62595 | 4675 MACARTHUR COURT SUITE 800 NEWPORT BEACH, CA 92660 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/23/2020 | Corrections Issued | MARK FERRARI |
| Deputy Steel/Welding | 11/17/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 11/24/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 12/2/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 12/2/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 12/2/2020 | Corrections Issued | MARK FERRARI |
| Deputy Reinf. Concrete | 12/3/2020 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 12/4/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 12/9/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 12/9/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/22/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 12/22/2020 | Approved | MARK FERRARI |
| Final | 1/21/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 1/21/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 1/21/2021 | Approved | MARK FERRARI |
| Final | 1/22/2021 | OK for CofC | MARK FERRARI |