Deputy Grading
|
7/19/2018
|
No Access for Inspection
|
FRED WOHLFARTH
|
|
Piling/Pier/Caisson
|
7/20/2018
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
7/20/2018
|
Approved
|
EDWIN GREGORYONA
|
|
Deputy Grading
|
7/23/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/23/2018
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
7/23/2018
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Grading
|
7/24/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/26/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
7/26/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/27/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
7/27/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/30/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
7/30/2018
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/31/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
7/31/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
8/13/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
8/13/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
8/23/2018
|
Approved
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
8/27/2018
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
8/30/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
9/4/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
9/7/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
9/10/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
9/12/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
9/12/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
9/12/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
9/14/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
9/24/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/1/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/3/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/4/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/5/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/9/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/9/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/10/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/10/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
10/11/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/15/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/15/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/15/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/16/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/16/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/17/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/17/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/18/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/19/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/19/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/24/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/25/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/26/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/30/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
10/30/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
10/30/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/31/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/31/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/1/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
11/1/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
11/2/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
11/8/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/9/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
11/20/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
11/30/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/4/2018
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
12/4/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/6/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
12/10/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
12/11/2018
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
12/13/2018
|
Corrections Issued
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
12/24/2018
|
No Access for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
1/2/2019
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
1/4/2019
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
1/7/2019
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
1/11/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Interior/Exterior Lathing
|
1/24/2019
|
Approved
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
2/20/2019
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
3/1/2019
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Final
|
9/18/2019
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
9/18/2019
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Final
|
9/18/2019
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
9/18/2019
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
9/18/2019
|
Approved
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
9/18/2019
|
SGSOV Approved
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
9/18/2019
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
9/18/2019
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
9/19/2019
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Final
|
1/19/2021
|
Conditional Approval
|
EDWIN GREGORYONA
|
|
Green Building Final
|
1/19/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
1/19/2021
|
Approved
|
EDWIN GREGORYONA
|