4911 W ROMAINE ST 90029
Certificate Information: 4911 W ROMAINE ST 90029
- Application / Permit
- 18016-10000-03296
- Plan Check / Job No.
- B18LA01974
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-story seismic retrofit per LAMC 93. INSTALL (2) CANTILEVERED COLUMN
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/27/2021
Permit Application Status History
| Submitted | 2/1/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2018 | HERNAN ARREOLA |
| Corrections Issued | 2/15/2018 | HERNAN ARREOLA |
| Quality Review Completed | 2/16/2018 | SAI KHUM |
| Building Plans Picked Up | 2/23/2018 | APPLICANT |
| Plan Check Approved | 3/29/2018 | HERNAN ARREOLA |
| Issued | 3/12/2020 | LADBS |
| OK for CofC | 4/13/2021 | MARK FERRARI |
| CofC Issued | 4/27/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/27/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Ace Construction Inc; Lic. No.: 809243-B | 11921 SHERMAN WAY NORTH HOLLYWOOD, CA 91605 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/18/2020 | Corrections Issued | MARK FERRARI |
| Pre-Inspection | 6/23/2020 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 9/16/2020 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 9/16/2020 | Approved | MARK FERRARI |
| Wood Frame | 9/16/2020 | Partial Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 9/18/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 9/18/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 9/18/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 10/15/2020 | Approved | MARK FERRARI |
| Wood Frame | 10/15/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 3/19/2021 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Not Ready | JONATHAN QUACH |
| Final | 4/7/2021 | Partial Inspection | JONATHAN QUACH |
| Final | 4/13/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 4/13/2021 | Approved | MARK FERRARI |