119 N HAYWORTH AVE 90048
Certificate Information: 119 N HAYWORTH AVE 90048
- Application / Permit
- 18016-10000-03233
- Plan Check / Job No.
- B18LA01932
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93 USING MOMENT FRAME WITH GRADE BEAM AT WEST SIDE AND SHEAR WALL WITH TIE BEAM AT SOUTH SIDE. NO CHANGE IN # OF AND DIMENSIONS OF PARKING STALLS. PARKING REQ'D CLEARANCES TO MAINTAIN.
- Permit Issued
- Issued on 1/21/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/12/2022
Permit Application Status History
| Submitted | 1/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2018 | PAUL PIERRE |
| Corrections Issued | 2/6/2018 | PAUL PIERRE |
| Quality Review Completed | 2/9/2018 | SAI KHUM |
| Building Plans Picked Up | 2/12/2018 | APPLICANT |
| Plan Check Approved | 4/24/2018 | PAUL PIERRE |
| Issued | 1/21/2020 | LADBS |
| OK for CofC | 10/12/2022 | WINSTON DUNNING |
| CofC Issued | 10/12/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/21/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | , ; Lic. No.: C82891 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/4/2022 | Approved | DARRYL ARNOLD |
| Deputy Other (see comments) | 2/18/2022 | Conditional Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 2/22/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 2/28/2022 | Partial Approval | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 3/2/2022 | Conditional Approval | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/25/2022 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 3/31/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Approved | BRUCE CAMPBELL |
| METHANE-Rough | 4/6/2022 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 4/6/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 4/6/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 4/25/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 10/5/2022 | Conditional Approval | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 10/5/2022 | Approved | BRUCE CAMPBELL |
| Final | 10/12/2022 | OK for CofC | WINSTON DUNNING |