1132 N GLENDALE BLVD 90026
Certificate Information: 1132 N GLENDALE BLVD 90026
- Application / Permit
- 18016-10000-02760
- Plan Check / Job No.
- B18LA01649
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- INTERIOR TENANT IMPROVEMENTS TO EXISTING SHELL SPACE 16,976 SF TO CHURCH, KITCHEN AND NEW OFFICE AREAS (NO EXTERIOR WORK UNDER THIS PERMIT).
- Permit Issued
- Issued on 4/11/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2018 | APPLICANT |
| Green Plans Picked Up | 2/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2018 | AUNG SOE |
| Disabled Access Plans Picked Up | 2/23/2018 | APPLICANT |
| Corrections Issued | 3/7/2018 | KRIKOR MANOUKIAN |
| Quality Review Completed | 4/2/2018 | HERNAN ARREOLA |
| Building Plans Picked Up | 4/3/2018 | APPLICANT |
| Plan Check Approved | 10/16/2018 | SERGIO SILVA |
| Issued | 4/11/2019 | LADBS |
| CofO in Progress | 9/21/2020 | RONALD PACHECO |
| Permit Finaled | 10/29/2020 | DAVID TSAU |
| CofO Issued | 10/29/2020 | DAVID TSAU |
| Permit Finaled | 10/29/2020 | DAVID TSAU |
Permit Application Clearance Information
| DAS Clearance | Cleared | 7/10/2018 | WAI LAU |
| Green Code | Cleared | 7/10/2018 | KATHRYN BUTTERWORTH |
| Fire Marshall Fire Life Safety | Cleared | 9/24/2018 | ANDREW KO |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2018 | MAHELET GEBEYHU |
| ZA Case | Cleared | 9/26/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 9/26/2018 | KIT AWAKUNI |
| Sewer availability | Cleared | 9/28/2018 | MICHAEL CASTILLO |
Contact Information
| Architect | Molsberry, Matthew Merrill; Lic. No.: C30536 | 2050 MAIN STREET SUITE 400 IRVINE, CA 92614 |
| Contractor | Smith And Severson Builders Llc; Lic. No.: 989943-B | 21072 BAKE PARKWAY SUITE 106 LAKE FOREST, CA 92630 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2019 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/20/2019 | Not Ready for Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 7/2/2019 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 7/2/2019 | Partial Inspection | JEFFREY FULTON |
| Insulation | 7/10/2019 | Partial Inspection | JEFFREY FULTON |
| Insulation | 8/9/2019 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 8/9/2019 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 9/4/2019 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 9/10/2019 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 9/12/2019 | Conditional Approval | JEFFREY FULTON |
| Light Gage Steel Frame | 9/24/2019 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 11/19/2019 | Corrections Issued | JEFFREY FULTON |
| Pre-Inspection | 11/25/2019 | No Access for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 11/27/2019 | No Access for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 12/2/2019 | Corrections Issued | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 12/3/2019 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 12/5/2019 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 12/26/2019 | Not Ready for Inspection | RONALD PACHECO |
| T-Bar Ceiling | 12/27/2019 | Not Ready for Inspection | RONALD PACHECO |
| T-Bar Ceiling | 1/3/2020 | Partial Approval | RONALD PACHECO |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2020 | Partial Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 2/11/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 2/14/2020 | Partial Inspection | RONALD PACHECO |
| T-Bar Ceiling | 4/23/2020 | Partial Inspection | JONATHAN QUACH |
| Final | 6/3/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Final | 6/3/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Rough | 6/3/2020 | Approved | RONALD PACHECO |
| Reinforced Concrete Frame | 6/3/2020 | Approved | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 6/3/2020 | SGSOV Approved | RONALD PACHECO |
| Smoke Detectors | 6/3/2020 | Not Ready for Inspection | RONALD PACHECO |
| Smoke Detectors | 8/13/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 8/28/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Final | 8/28/2020 | Approved | RONALD PACHECO |
| Smoke Detectors | 8/28/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 9/8/2020 | Not Ready for Inspection | RONALD PACHECO |
| Smoke Detectors | 9/8/2020 | Approved | RONALD PACHECO |
| Final | 9/15/2020 | Partial Approval | RONALD PACHECO |