4354 W DON LUIS DR 90008
Certificate Information: 4354 W DON LUIS DR 90008
- Application / Permit
- 18014-70000-07153
- Plan Check / Job No.
- B18SL01826
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st and 2nd STORY ADDITION AND REMODEL (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Current Status
- CofO Issued on 11/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2019 | MONICA RAMIREZ |
| Corrections Issued | 1/7/2019 | MONICA RAMIREZ |
| Quality Review Completed | 1/14/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 1/17/2019 | APPLICANT |
| Plan Check Approved | 3/11/2019 | MONICA RAMIREZ |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 11/7/2025 | LUIS CASTRO |
| No Progress | 11/7/2025 | MICHAEL LEWIS |
| CofO in Progress | 11/7/2025 | MICHAEL LEWIS |
| Permit Finaled | 11/12/2025 | DEROLD HAUFF |
| CofO Issued | 11/12/2025 | DEROLD HAUFF |
| Permit Finaled | 11/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2019 | ELENA LOPEZ |
| Hydrant and Access approval | Cleared | 3/7/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 3/7/2019 | ELENA LOPEZ |
| Green Code | Cleared | 3/8/2019 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 3/8/2019 | MITESH PATEL |
| Grading Pre-Inspection | Cleared | 3/11/2019 | MONICA RAMIREZ |
| Roof/Waste drainage to street | Cleared | 3/11/2019 | KARAN PATEL |
Contact Information
| Architect | Johnson,, David Michael; Lic. No.: C18045 | 3638 AUREOLA BLVD LOS ANGELES, CA 90008 |
| Contractor | J B New Construction Inc; Lic. No.: 923970-B | 13923 S CRENSHAW BLVD HAWTHORNE, CA 90250 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2020 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 11/18/2020 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2021 | Corrections Issued | DAVID FEILER |
| Deputy Wood Construction | 2/17/2021 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 2/24/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 6/7/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 6/7/2021 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 6/29/2021 | Approved | ALFREDO BALANDRA |
| Insulation | 7/8/2021 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 7/20/2021 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 7/22/2021 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | DAVID FEILER |
| Green Building Rough | 8/6/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 8/6/2021 | Approved | DAVID FEILER |
| Drywall Nailing | 8/18/2021 | Approved | DAVID FEILER |
| Insulation | 8/18/2021 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 3/15/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 1/25/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 1/30/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 1/30/2023 | No Access for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/30/2023 | SGSOV Not Required | ANTHONY EGSON |
| Pre-Inspection | 10/7/2024 | Partial Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 10/16/2025 | Approved | LUIS CASTRO |
| Final | 10/16/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 10/16/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 10/16/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 10/16/2025 | Approved | LUIS CASTRO |
| Smoke Detectors | 10/16/2025 | Approved | LUIS CASTRO |
| Final | 11/5/2025 | OK to Issue CofO | LUIS CASTRO |
| Green Building Final | 11/5/2025 | Approved | LUIS CASTRO |