13437 1/2 W BEAVER ST 91342

Certificate Information: 13437 1/2 W BEAVER ST 91342

Application / Permit
18014-70000-06606
Plan Check / Job No.
B18SL01697
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF (E) DETACHED REC ROOM INTO AN ADU PER AB494 AND SB229. PER ENGR DESIGN
Permit Issued
Issued on 4/17/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2018 APPLICANT
Assigned to Plan Check Engineer 11/16/2018 LUKE GONZALES
Corrections Issued 11/16/2018 LUKE GONZALES
Plan Check Approved 4/10/2019 LUKE GONZALES
Issued 4/17/2019 LADBS
CofO in Progress 11/25/2020 MISAEL ESPARZA
CofO Issued 12/19/2020 MICHAEL SMITH
Permit Finaled 12/19/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/19/2018 CELINA MORENO
Construction near power lines Cleared 3/7/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 4/9/2019 JEANETTE VONG
Low Impact Development Cleared 4/9/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 4/9/2019 JEANETTE VONG
Sewer availability Cleared 4/9/2019 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/23/2019 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 1/17/2020 Partial Approval CHARLES POWELL
Green Building Rough 1/17/2020 Not Ready for Inspection CHARLES POWELL
Wood Frame 1/17/2020 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 2/19/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 2/19/2020 Not Ready for Inspection MICHEL ABAJAN
Pre-Inspection 2/27/2020 Approved MICHEL ABAJAN
Insulation 3/9/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/9/2020 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 3/19/2020 Approved TROY SANDERS
Interior/Exterior Lathing 3/19/2020 Approved TROY SANDERS
Interior/Exterior Lathing 3/25/2020 Approved TROY SANDERS
Final 7/6/2020 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 7/6/2020 No Access for Inspection GREGG CUMMINGS
Green Building Final 7/6/2020 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 7/6/2020 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/6/2020 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 7/6/2020 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 7/6/2020 Not Ready for Inspection GREGG CUMMINGS
Final 9/25/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 9/25/2020 Approved MISAEL ESPARZA
Green Building Final 9/25/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/25/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/25/2020 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 9/25/2020 Approved MISAEL ESPARZA
Wood Frame 9/25/2020 Approved MISAEL ESPARZA
Final 11/2/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 11/2/2020 Approved MISAEL ESPARZA
Final 11/24/2020 OK to Issue CofO MISAEL ESPARZA