1613 W 66TH ST 90047
Certificate Information: 1613 W 66TH ST 90047
- Application / Permit
- 18014-70000-06329
- Plan Check / Job No.
- B18SL01623
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND ADDITION FOR ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2018 | JOSHUA DIAZ |
| Corrections Issued | 11/5/2018 | JOSHUA DIAZ |
| Plan Check Approved | 1/30/2020 | RICARDO RAMIREZ |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 7/26/2021 | FREDDIE RIVERA |
| Permit Finaled | 7/27/2021 | DEROLD HAUFF |
| CofO Issued | 7/27/2021 | DEROLD HAUFF |
| Permit Finaled | 7/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/14/2019 | RIDWAN HARDY |
| Address approval | Cleared | 1/27/2020 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 1/27/2020 | CATHERINE ADROVER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 3/6/2020 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/6/2020 | Corrections Issued | FREDDIE RIVERA |
| Sewer | 3/6/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/31/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 3/31/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/27/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/27/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 8/27/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/28/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/28/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 9/28/2020 | Approved | FREDDIE RIVERA |
| Insulation | 10/5/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 10/30/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/30/2020 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/12/2021 | Approved | FREDDIE RIVERA |
| Gas Test | 4/12/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 4/21/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 4/21/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 4/21/2021 | Approved | FREDDIE RIVERA |
| HVAC-Final | 5/5/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 5/17/2021 | Corrections Issued | RICHARD ROBLES |
| Green Building Final | 5/17/2021 | Approved | RICHARD ROBLES |
| SGSOV-Seismic Gas S/O Valve | 5/17/2021 | SGSOV Approved | RICHARD ROBLES |
| Final | 6/2/2021 | OK to Issue CofO | FREDDIE RIVERA |