2005 W 78TH ST 90047

Certificate Information: 2005 W 78TH ST 90047

Application / Permit
18014-70000-06188
Plan Check / Job No.
B18SL01578
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
18' X 16' SECOND STORY ADDITION TO (E) 19' X 16'DETACHED GARAGE AND (E) 24' X 18' RECREATION ROOM ALL COVERTED TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 7/18/2019
Issuing Office
South Los Angeles
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2018 APPLICANT
Assigned to Plan Check Engineer 11/30/2018 ROSENDO MEDINA
Corrections Issued 12/6/2018 ROSENDO MEDINA
Quality Review Completed 12/7/2018 MOHAMMAD FIROUZBAKHT
Green Plans Picked Up 12/11/2018 APPLICANT
Applicant returned to address corrections 5/24/2019 ROSENDO MEDINA
Plan Check Approved 5/29/2019 ROSENDO MEDINA
Issued 7/18/2019 LADBS
CofO in Progress 6/15/2022 ENRIQUE MIRELES
Permit Finaled 7/23/2022 DEROLD HAUFF
CofO Issued 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/30/2019 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 1/30/2019 JAMES MORALEZ
Sewer availability Cleared 1/30/2019 JAMES MORALEZ
Construction near power lines Cleared 3/18/2019 RIDWAN HARDY
Green Code Cleared 5/14/2019 SARAH ABOULHOSN
Low Impact Development Cleared 5/24/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/24/2019 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,
Engineer Basso,, Alexandre; Lic. No.: C77670 7231 SUMMITROSE ST      TUJUNGA, CA 91042

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/26/2019 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 7/31/2019 Conditional Approval FREDDIE RIVERA
Special/Order Compliance 7/31/2019 Approved PAUL BECKER
Footing/Foundation/Slab 10/11/2019 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/27/2020 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 5/27/2020 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 5/27/2020 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/2/2020 Approved FREDDIE RIVERA
Footing/Foundation/Slab 6/2/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 10/19/2020 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 10/19/2020 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 10/28/2020 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 10/28/2020 Partial Approval FREDDIE RIVERA
Green Building Rough 10/28/2020 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 10/28/2020 Partial Approval FREDDIE RIVERA
Insulation 11/5/2020 Partial Approval FREDDIE RIVERA
Wood Frame 5/10/2021 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 7/23/2021 Not Ready for Inspection ANDREW BEELI
PLUMBING-Rough 7/23/2021 Not Ready for Inspection ANDREW BEELI
Wood Frame 7/23/2021 Corrections Issued ANDREW BEELI
ELECTRICAL-Rough 8/2/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 8/2/2021 Approved FREDDIE RIVERA
Pre-Inspection 8/2/2021 Corrections Issued FREDDIE RIVERA
Wood Frame 8/2/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 8/11/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 8/11/2021 Approved FREDDIE RIVERA
Wood Frame 8/11/2021 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Approved FREDDIE RIVERA
Pre-Inspection 8/23/2021 Partial Inspection JESUS PINEDA
Shower Pan 8/23/2021 Corrections Issued FREDDIE RIVERA
Wood Frame 8/23/2021 Approved FREDDIE RIVERA
Insulation 8/26/2021 Approved CALEB MEISTER
Shower Pan 8/26/2021 Approved CALEB MEISTER
Drywall Nailing 9/13/2021 Approved JESUS PINEDA
Green Building Rough 9/13/2021 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/14/2022 Approved ENRIQUE MIRELES
Final 3/14/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/14/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/14/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 3/14/2022 Approved ENRIQUE MIRELES
Final 5/16/2022 Corrections Issued ENRIQUE MIRELES
Final 6/15/2022 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 6/15/2022 Approved ENRIQUE MIRELES