857 E 106TH ST 90002

Certificate Information: 857 E 106TH ST 90002

Application / Permit
18014-70000-05489
Plan Check / Job No.
B18SL01378
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 ADDITION TO (E) GARAGE AND DEMOLISH (E) COVERED PATIO
Permit Issued
Issued on 9/12/2019
Issuing Office
Metro
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2018 APPLICANT
Assigned to Plan Check Engineer 10/25/2018 MONICA RAMIREZ
Green Plans Picked Up 10/31/2018 APPLICANT
Corrections Issued 11/5/2018 MONICA RAMIREZ
Quality Review Completed 11/14/2018 BILL STUTSMAN
Building Plans Picked Up 11/19/2018 APPLICANT
Applicant returned to address corrections 4/26/2019 MONICA RAMIREZ
Plan Check Approved 8/27/2019 MONICA RAMIREZ
Issued 9/12/2019 LADBS
CofO in Progress 5/28/2024 BEN MOLSTAD
Permit Finaled 5/29/2024 ANSON MAGLASANG
CofO Issued 5/29/2024 ANSON MAGLASANG
Permit Finaled 5/29/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/18/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/29/2019 JEANETTE VONG
Green Code Cleared 1/29/2019 KHEDER ALRAZAA
Hydrant and Access approval Cleared 1/29/2019 GILBERT URREA
Sewer availability Cleared 1/29/2019 JEANETTE VONG
Low Impact Development Cleared 3/21/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/26/2019 ELENA LOPEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/23/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/5/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/17/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/8/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 9/15/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/20/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 7/5/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/19/2022 Approved JOHN KLARIN
Green Building Rough 7/19/2022 Approved JOHN KLARIN
Insulation 7/19/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 7/19/2022 Approved JOHN KLARIN
Drywall Nailing 7/22/2022 Approved JOHN KLARIN
Shower Pan 8/19/2022 Approved JOHN KLARIN
Shower Pan 11/8/2022 Approved JOHN KLARIN
Gas Test 5/3/2023 Approved JAMES CHAVEZ
Underground Mechanical 5/3/2023 Partial Approval JAMES CHAVEZ
Sewer 6/14/2023 Approved JOHN KLARIN
ELECTRICAL-Final 9/22/2023 Approved JOHN KLARIN
Final 9/22/2023 Corrections Issued JOHN KLARIN
Green Building Final 9/22/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 9/22/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 9/22/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 9/22/2023 Approved JOHN KLARIN
Final 10/3/2023 Corrections Issued JOHN KLARIN
Green Building Final 10/3/2023 Approved JOHN KLARIN
ELECTRICAL-Final 5/20/2024 Corrections Issued BEN MOLSTAD
Final 5/20/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 5/20/2024 Approved BEN MOLSTAD
PLUMBING-Final 5/20/2024 Corrections Issued BEN MOLSTAD
Final 5/24/2024 OK to Issue CofO BEN MOLSTAD
PLUMBING-Final 5/24/2024 Approved BEN MOLSTAD
Service/Power Release 5/28/2024 Approved BEN MOLSTAD