2030 W YOSEMITE DR 90041

Certificate Information: 2030 W YOSEMITE DR 90041

Application / Permit
18014-70000-05477
Plan Check / Job No.
B18SL01375
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERSION OF (E) DETACHED GARAGE INTO ADU PER AB494 AND SB229. "COMPLY WITH DEPARTMENT ORDER effective date 05/13/2013. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 1/23/2020
Issuing Office
South Los Angeles
Current Status
CofO in Progress on 3/15/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/25/2018 APPLICANT
Assigned to Plan Check Engineer 9/25/2018 LUKE GONZALES
Corrections Issued 9/25/2018 LUKE GONZALES
Plan Check Approved 1/23/2020 LUKE GONZALES
Issued 1/23/2020 LADBS
CofO in Progress 3/15/2022 MARK VAN SLOOTEN

Permit Application Clearance Information

Address approval Cleared 9/25/2018 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/25/2018 CELINA MORENO
Sewer availability Cleared 9/25/2018 CELINA MORENO
Grading Pre-Inspection Cleared 7/18/2019 PATRICK MISCHLICH
Low Impact Development Cleared 7/18/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/18/2019 ERIK BEASLEY
Construction near power lines Cleared 10/26/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/7/2021 Approved MARK VAN SLOOTEN
Pre-Inspection 6/29/2021 Approved MARK VAN SLOOTEN
Footing/Foundation/Slab 7/19/2021 Approved MARK VAN SLOOTEN
BUILDING-Rough-Frame 8/31/2021 Corrections Issued MARK VAN SLOOTEN
ELECTRICAL-Rough 8/31/2021 Approved MARK VAN SLOOTEN
Green Building Rough 8/31/2021 Approved MARK VAN SLOOTEN
PLUMBING-Rough 8/31/2021 Approved MARK VAN SLOOTEN
BUILDING-Rough-Frame 9/8/2021 Approved MARK VAN SLOOTEN
Insulation 9/8/2021 Approved MARK VAN SLOOTEN
Drywall Nailing 9/9/2021 Approved MARK VAN SLOOTEN
Interior/Exterior Lathing 9/9/2021 Approved MARK VAN SLOOTEN
Final 2/14/2022 Conditional Approval MARK VAN SLOOTEN
Green Building Final 2/14/2022 Approved MARK VAN SLOOTEN
SGSOV-Seismic Gas S/O Valve 2/14/2022 SGSOV Approved MARK VAN SLOOTEN
Smoke Detectors 2/14/2022 Approved MARK VAN SLOOTEN