111 E 82ND ST 90003
Certificate Information: 111 E 82ND ST 90003
- Application / Permit
- 18014-70000-05008
- Plan Check / Job No.
- B18SL01275
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 2nd FLOOR ADDITION AND A NEW 2ND FLOOR DECK , INCREASE THE SIZE OF UNIT NUMBER 3 ON 2ND FLOOR FROM 2BR TO 3BR.
- Permit Issued
- Issued on 1/6/2020
- Issuing Office
- Metro
- Current Status
- Issued on 1/6/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/31/2018 | APPLICANT |
| Green Plans Picked Up | 10/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2018 | RAHEL BEYENE |
| Corrections Issued | 10/18/2018 | RAHEL BEYENE |
| Quality Review Completed | 10/25/2018 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/14/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 5/10/2019 | APPLICANT |
| Applicant returned to address corrections | 6/28/2019 | RAHEL BEYENE |
| Applicant returned to address corrections | 8/15/2019 | RAHEL BEYENE |
| Plan Check Approved | 11/13/2019 | RAHEL BEYENE |
| Issued | 1/6/2020 | LADBS |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/11/2019 | MOTOUMI SASAKI |
| Coastal Zone | Cleared | 2/11/2019 | MOTOUMI SASAKI |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2019 | JEANETTE VONG |
| Green Code | Cleared | 2/11/2019 | KHEDER ALRAZAA |
| Housing rent stabilization | Cleared | 2/11/2019 | STEVEN HOFSTAD |
| Hydrant and Access approval | Cleared | 2/11/2019 | GILBERT URREA |
| Sewer availability | Cleared | 2/11/2019 | JEANETTE VONG |
| Specific Plan | Cleared | 2/11/2019 | MOTOUMI SASAKI |
| Project located in CRA area | Cleared | 3/8/2019 | JIM URQUHART |
| Low Impact Development | Cleared | 5/9/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/9/2019 | ELAINE LEI |
| DAS Clearance | Cleared | 7/10/2019 | ELIZABETH TOMS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/21/2020 | Not Ready for Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 5/28/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 6/10/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 6/12/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Green Building Rough | 9/22/2020 | Not Ready for Inspection | LANNY MERRICK |
| Wood Frame | 9/22/2020 | Partial Approval | LANNY MERRICK |
| Insulation | 10/27/2020 | Approved | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 11/10/2020 | Approved | LEOPOLDO MENDOZA |
| Drywall Nailing | 3/18/2021 | Approved | LANNY MERRICK |
| Green Building Rough | 3/18/2021 | Approved | LANNY MERRICK |
| Final | 5/10/2022 | No Access for Inspection | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 5/10/2022 | No Access for Inspection | RUSSELL BONVOULOIR |
| Green Building Final | 5/10/2022 | No Access for Inspection | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Not Ready | RUSSELL BONVOULOIR |
| Smoke Detectors | 5/10/2022 | No Access for Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 5/10/2022 | No Access for Inspection | RUSSELL BONVOULOIR |
| Final | 6/2/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 6/2/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Final | 6/2/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 6/2/2022 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 6/2/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 11/8/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 11/19/2024 | No Access for Inspection | DARRYL ARNOLD |
| Final | 11/20/2024 | Conditional Approval | DARRYL ARNOLD |