6941 S GLASGOW AVE 90045

Certificate Information: 6941 S GLASGOW AVE 90045

Application / Permit
18014-70000-04537
Plan Check / Job No.
B18SL01190
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ADDITION TO (E) APARTMENT AT UNIT 6941 FOR A (N) BATHROOM. PER ENGINEER DESIGN
Permit Issued
Issued on 9/10/2018
Issuing Office
South Los Angeles
Current Status
CofO Issued on 2/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2018 APPLICANT
Assigned to Plan Check Engineer 8/9/2018 LUKE GONZALES
Corrections Issued 8/9/2018 LUKE GONZALES
Plan Check Approved 9/6/2018 JOSHUA DIAZ
Issued 9/10/2018 LADBS
CofO in Progress 2/11/2022 GRANT WOODS
Permit Finaled 2/11/2022 DAVID TSAU
CofO Issued 2/11/2022 DAVID TSAU
Permit Finaled 2/11/2022 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 8/16/2018 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 8/16/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/31/2018 ROBYN STEELE
Hold Cleared 8/31/2018 LOURDES RAMIRO
Grading Pre-Inspection Cleared 9/4/2018 LUKE GONZALES
Specific Plan Cleared 9/4/2018 MOHAMMAD HASAN

Contact Information

Contractor Ntc Development; Lic. No.: 897288-B 8935 S BROADWAY      LOS ANGELES, CA 90003
Engineer Cooke, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/11/2018 No Access for Inspection ALAN NOVAK
METHANE-Barrier 9/11/2018 No Access for Inspection ALAN NOVAK
METHANE-Subgrade 9/11/2018 No Access for Inspection ALAN NOVAK
Excavation/Setback/Form/Re-Bar 9/12/2018 Not Ready for Inspection ALAN NOVAK
Footing/Foundation/Slab 9/14/2018 Not Ready for Inspection ALAN NOVAK
METHANE-Barrier 9/14/2018 Not Ready for Inspection ALAN NOVAK
METHANE-Subgrade 9/14/2018 Not Ready for Inspection ALAN NOVAK
Footing/Foundation/Slab 9/18/2018 Approved ALAN NOVAK
METHANE-Barrier 9/18/2018 Approved ALAN NOVAK
METHANE-Subgrade 9/18/2018 Approved ALAN NOVAK
Floor/Roof Diaphrgm/Shear Wall 10/4/2018 Corrections Issued ALAN NOVAK
Green Building Rough 10/18/2018 Approved ALAN NOVAK
METHANE-Rough 10/18/2018 Approved ALAN NOVAK
Wood Frame 10/18/2018 Not Ready for Inspection ALAN NOVAK
Insulation 10/22/2018 Partial Approval ALAN NOVAK
Wood Frame 10/22/2018 Partial Approval ALAN NOVAK
Deputy Drilled-In Anchors 11/6/2018 Conditional Approval ALAN NOVAK
Wood Frame 11/8/2018 Not Ready for Inspection ALAN NOVAK
Insulation 11/30/2018 Approved ALAN NOVAK
Wood Frame 11/30/2018 Approved ALAN NOVAK
Drywall Nailing 12/11/2018 Approved ALAN NOVAK
Interior/Exterior Lathing 12/11/2018 Approved ALAN NOVAK
Final 1/22/2019 Not Ready for Inspection ALAN NOVAK
Green Building Final 1/22/2019 Not Ready for Inspection ALAN NOVAK
Smoke Detectors 1/22/2019 Not Ready for Inspection ALAN NOVAK
Final 2/1/2019 Not Ready for Inspection DERRICK SPENCER
Green Building Final 2/1/2019 Approved DERRICK SPENCER
Smoke Detectors 2/1/2019 Approved DERRICK SPENCER
Final 9/13/2021 Partial Inspection GRANT WOODS
Final 2/11/2022 Conditional Approval GRANT WOODS