1231 W 46TH ST 90037
Certificate Information: 1231 W 46TH ST 90037
- Application / Permit
- 18014-70000-04116
- Plan Check / Job No.
- B18SL01080
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT THE FRONT AND REAR OF (E) SFD WITH BASEMENT TO CREATE 2 NEW BEDROOMS. "COMPLY WITH DEPT ORDER. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2018 | LUKE GONZALES |
| Corrections Issued | 7/19/2018 | LUKE GONZALES |
| Plan Check Approved | 12/24/2019 | RICARDO RAMIREZ |
| Issued | 1/23/2023 | APPLICANT |
| Refund in Progress | 5/4/2023 | SELENIA GARCIA |
| Refund Closed | 5/4/2023 | SELENIA GARCIA |
| Issued | 5/4/2023 | SELENIA GARCIA |
| CofO in Progress | 1/2/2026 | DANIEL GONZALEZ |
| Permit Finaled | 4/7/2026 | CLAUDIO MORENO |
| Permit Finaled | 4/7/2026 | CLAUDIO MORENO |
| CofO Issued | 4/7/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2018 | NAZILA NOORIFAR |
| Roof/Waste drainage to street | Cleared | 7/24/2018 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 7/24/2018 | NAZILA NOORIFAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Tucker,, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/24/2023 | Corrections Issued | MARIO CUEVAS |
| Pre-Inspection | 2/2/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Footing/Foundation/Slab | 3/9/2023 | Corrections Issued | MARIO CUEVAS |
| Footing/Foundation/Slab | 12/26/2023 | Corrections Issued | DANIEL GONZALEZ |
| Pre-Inspection | 2/20/2025 | Corrections Issued | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 6/6/2025 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 6/6/2025 | Corrections Issued | DANIEL GONZALEZ |
| Green Building Rough | 6/6/2025 | Partial Inspection | DANIEL GONZALEZ |
| Pre-Inspection | 10/8/2025 | Corrections Issued | DANIEL GONZALEZ |
| Underground Mechanical | 10/8/2025 | Partial Approval | DANIEL GONZALEZ |
| Masonry Wall/Backfill | 10/22/2025 | Partial Approval | DANIEL GONZALEZ |
| Reinforced Masonry Frame | 11/4/2025 | Partial Approval | DANIEL GONZALEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Approved | DANIEL GONZALEZ |
| Underground Mechanical | 11/25/2025 | Approved | DANIEL GONZALEZ |
| Pre-Inspection | 12/19/2025 | Approved | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 12/29/2025 | Approved | DANIEL GONZALEZ |
| Final | 12/29/2025 | Conditional Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 12/29/2025 | Approved | DANIEL GONZALEZ |
| Green Building Final | 12/29/2025 | Approved | DANIEL GONZALEZ |
| Green Building Rough | 12/29/2025 | Approved | DANIEL GONZALEZ |
| SGSOV-Seismic Gas S/O Valve | 12/29/2025 | SGSOV Approved | DANIEL GONZALEZ |
| Smoke Detectors | 12/29/2025 | Approved | DANIEL GONZALEZ |
| Final | 1/2/2026 | OK to Issue CofO | DANIEL GONZALEZ |