5731 W ALADDIN ST 90008

Certificate Information: 5731 W ALADDIN ST 90008

Application / Permit
18014-70000-03950
Plan Check / Job No.
B18SL01029
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1 STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING TO CREATE NEW ENTRY WAY, EXPAND EXISTING KITCHEN/LIVING AREA AND CONVERT A PORTION OF EXISTING GARAGE TO 1 NEW BEDROOM. ALL WORK TO BE DONE PER ENGINEER OF RECORD.
Permit Issued
Issued on 10/11/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2018 APPLICANT
Green Plans Picked Up 7/25/2018 APPLICANT
Assigned to Plan Check Engineer 8/16/2018 MICHAEL LOPEZ
Corrections Issued 8/20/2018 MICHAEL LOPEZ
Quality Review Completed 8/24/2018 DAVID CHANG
Building Plans Picked Up 8/28/2018 APPLICANT
Applicant returned to address corrections 7/2/2019 MICHAEL LOPEZ
Plan Check Approved 7/8/2019 MICHAEL LOPEZ
Issued 10/11/2019 LADBS
CofO in Progress 12/23/2024 ENRIQUE MIRELES
Permit Finaled 12/26/2024 DEROLD HAUFF
CofO Issued 12/26/2024 DEROLD HAUFF
Permit Finaled 12/26/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/29/2018 CELINA MORENO
Roof/Waste drainage to street Cleared 8/29/2018 CELINA MORENO
Sewer availability Cleared 8/29/2018 CELINA MORENO
Green Code Cleared 9/6/2018 KHEDER ALRAZAA
Construction near power lines Cleared 5/9/2019 WALTER RAMIREZ
Construction within easement Cleared 5/9/2019 WALTER RAMIREZ
Grading Pre-Inspection Cleared 7/2/2019 TODD MALAND

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C29787       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/24/2019 Conditional Approval COREY HUPP
Footing/Foundation/Slab 10/29/2019 Not Ready for Inspection COREY HUPP
METHANE-Barrier 10/29/2019 Approved COREY HUPP
METHANE-Subgrade 10/29/2019 Approved COREY HUPP
Footing/Foundation/Slab 11/6/2019 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 11/8/2019 Approved COREY HUPP
BUILDING-Rough-Frame 3/11/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Final 3/11/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 3/11/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Final 3/18/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Final 3/18/2020 Corrections Issued COREY HUPP
Special/Order Compliance 3/27/2020 Corrections Issued RUBEN SALAS
Gas Test 4/3/2020 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 4/3/2020 Not Ready for Inspection SABAS ALONSO
Rough-Elec/Plmb/HVAC 4/3/2020 Not Ready for Inspection SABAS ALONSO
Wood Frame 4/3/2020 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 4/27/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 4/27/2020 Approved FREDDIE RIVERA
Gas Test 4/27/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 4/27/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Final 4/27/2020 Not Ready for Inspection FREDDIE RIVERA
Wood Frame 4/27/2020 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 5/5/2020 Approved FREDDIE RIVERA
Gas Test 5/5/2020 Approved FREDDIE RIVERA
Green Building Rough 5/5/2020 Approved FREDDIE RIVERA
HVAC-Final 5/5/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 5/5/2020 Approved FREDDIE RIVERA
Insulation 5/13/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 5/13/2020 Approved SABAS ALONSO
Drywall Nailing 5/27/2020 Approved SABAS ALONSO
Gas Test 5/27/2020 Not Ready for Inspection SABAS ALONSO
Final 1/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 1/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/11/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 1/11/2024 Approved ALIZAH MAYAGOITIA
Final 5/30/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Final 5/30/2024 Corrections Issued ANTHONY EGSON
Final 10/17/2024 Partial Inspection ANTHONY EGSON
Green Building Final 10/17/2024 Not Ready for Inspection ANTHONY EGSON
Final 12/17/2024 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 12/17/2024 Approved ENRIQUE MIRELES