917 W 50TH ST 90037

Certificate Information: 917 W 50TH ST 90037

Application / Permit
18014-70000-03926
Plan Check / Job No.
B18SL01025
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-STORY ADDITION TO (E) 1-CAR GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 11/9/2018
Issuing Office
South Los Angeles
Current Status
CofO Issued on 11/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2018 APPLICANT
Assigned to Plan Check Engineer 8/3/2018 JOSHUA DIAZ
Corrections Issued 8/13/2018 JOSHUA DIAZ
Quality Review Completed 8/22/2018 WESLEY FARRELL
Building Plans Picked Up 8/28/2018 APPLICANT
Green Plans Picked Up 8/28/2018 APPLICANT
Applicant returned to address corrections 11/8/2018 JOSHUA DIAZ
Plan Check Approved 11/9/2018 JOSHUA DIAZ
Issued 11/9/2018 LADBS
CofO in Progress 11/19/2021 PAUL BECKER
Permit Finaled 11/19/2021 BRUCE TODD
CofO Issued 11/19/2021 BRUCE TODD
Permit Finaled 11/19/2021 BRUCE TODD

Permit Application Clearance Information

"Q" conditions Cleared 9/24/2018 YOVANA PEREZ
Address approval Cleared 9/24/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 9/24/2018 STEVE MELGAR
Highway dedication Cleared 9/24/2018 STEVE MELGAR
Hydrant and Access approval Cleared 9/24/2018 ROBERT DUFF
Sewer availability Cleared 9/24/2018 STEVE MELGAR
Green Code Cleared 11/6/2018 KHEDER ALRAZAA
Low Impact Development Cleared 11/7/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/7/2018 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/30/2019 Not Ready for Inspection COREY HUPP
Pre-Inspection 4/30/2019 Partial Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 12/27/2019 Not Ready for Inspection DEROLD HAUFF
Excavation/Setback/Form/Re-Bar 12/27/2019 Partial Inspection ELMER BLAND
Footing/Foundation/Slab 12/27/2019 Not Ready for Inspection DEROLD HAUFF
Special/Order Compliance 12/27/2019 Partial Inspection ELMER BLAND
Underground Mechanical 12/27/2019 Partial Approval DEROLD HAUFF
Underground Mechanical 12/27/2019 Partial Inspection ELMER BLAND
Underground Mechanical 4/13/2020 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 4/23/2020 Not Ready for Inspection ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 4/24/2020 Conditional Approval SCOTT FINNILA
Special/Order Compliance 4/27/2020 Corrections Issued ELMER BLAND
Excavation/Setback/Form/Re-Bar 4/30/2020 Approved PAUL BECKER
Underground Mechanical 4/30/2020 Approved PAUL BECKER
Special/Order Compliance 5/4/2020 Approved PAUL BECKER
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Partial Approval PAUL BECKER
Footing/Foundation/Slab 7/9/2020 Partial Approval PAUL BECKER
Floor/Roof Diaphrgm/Shear Wall 8/27/2020 Partial Approval PAUL BECKER
Interior/Exterior Lathing 9/16/2020 Approved PAUL BECKER
ELECTRICAL-Rough 10/1/2020 Approved PAUL BECKER
HVAC-Rough 10/1/2020 Corrections Issued PAUL BECKER
PLUMBING-Rough 10/1/2020 Approved PAUL BECKER
Insulation 10/6/2020 Approved PAUL BECKER
Interior/Exterior Lathing 10/6/2020 Approved PAUL BECKER
Drywall Nailing 10/23/2020 Approved PAUL BECKER
Rough-Elec/Plmb/HVAC 10/23/2020 Approved PAUL BECKER
BUILDING-Rough-Frame 2/19/2021 Approved PAUL BECKER
Final 2/19/2021 Not Ready for Inspection PAUL BECKER
Footing/Foundation/Slab 2/19/2021 Approved PAUL BECKER
Green Building Final 2/19/2021 Not Ready for Inspection PAUL BECKER
Green Building Rough 2/19/2021 Approved PAUL BECKER
SGSOV-Seismic Gas S/O Valve 2/19/2021 SGSOV Approved PAUL BECKER
Smoke Detectors 2/19/2021 Approved PAUL BECKER
Final 11/16/2021 OK to Issue CofO PAUL BECKER
Green Building Final 11/16/2021 Approved PAUL BECKER