232-234 E 67TH ST 90003

Certificate Information: 232-234 E 67TH ST 90003

Application / Permit
18014-70000-03467
Plan Check / Job No.
B18SL00923
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
2-STORY ADDITION AND CONVERT SINGLE FAMILY DWELLING TO DUPLEX
Permit Issued
Issued on 3/14/2019
Issuing Office
Metro
Current Status
CofO Issued on 1/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2018 APPLICANT
Green Plans Picked Up 7/18/2018 APPLICANT
Assigned to Plan Check Engineer 7/19/2018 AUNG SOE
Corrections Issued 7/23/2018 AUNG SOE
Building Plans Picked Up 8/10/2018 APPLICANT
Quality Review Completed 10/17/2018 DAVID CHANG
Applicant returned to address corrections 12/26/2018 AUNG SOE
Plan Check Approved 3/14/2019 AUNG SOE
Issued 3/14/2019 LADBS
CofO in Progress 1/8/2020 EUGENE CASSIDY
Permit Finaled 1/17/2020 DEROLD HAUFF
CofO Issued 1/17/2020 DEROLD HAUFF
Permit Finaled 1/17/2020 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 9/17/2018 COLIN LOREDO
Address approval Cleared 10/23/2018 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 10/23/2018 JEANETTE VONG
Hydrant and Access approval Cleared 10/23/2018 ROBERT DUFF
Sewer availability Cleared 10/23/2018 JEANETTE VONG
Low Impact Development Cleared 11/9/2018 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/9/2018 JAMES MORALEZ

Contact Information

Contractor Frisco Investment Group Inc; Lic. No.: 1038932-B 2851 W 120TH ST   E112    HAWTHRONE, CA 90250
Engineer Nzeogu,, Godfrey Iheanacho; Lic. No.: C61921 1507 EAST GLADWICK ST      CARSON, CA 90746

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/19/2019 Partial Approval VICTOR PUKHALSKY
Footing/Foundation/Slab 5/6/2019 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/6/2019 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/10/2019 Approved BOB DUNN
Floor/Roof Diaphrgm/Shear Wall 6/18/2019 Partial Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 7/5/2019 No Access for Inspection ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 7/17/2019 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 7/17/2019 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 7/17/2019 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 7/17/2019 Approved PAUL BECKER
BUILDING-Rough-Frame 7/30/2019 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 7/30/2019 Not Ready for Inspection EUGENE CASSIDY
Gas Test 7/30/2019 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 7/30/2019 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 7/30/2019 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 7/30/2019 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 7/30/2019 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 8/5/2019 Approved JOHN KLARIN
PLUMBING-Rough 8/5/2019 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/6/2019 Approved BOB DUNN
Green Building Rough 8/6/2019 Approved BOB DUNN
HVAC-Rough 8/6/2019 Approved BOB DUNN
HVAC-Rough 8/7/2019 Approved JOHN KLARIN
Insulation 8/7/2019 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 8/7/2019 Approved JOHN KLARIN
Insulation 8/13/2019 Approved JOHN KLARIN
Drywall Nailing 8/19/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 8/22/2019 Approved ALEJANDRO DE ARTOLA
Sewer 9/20/2019 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/25/2019 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 9/25/2019 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/25/2019 Corrections Issued EUGENE CASSIDY
Final 10/25/2019 Not Ready for Inspection EUGENE CASSIDY
Gas Test 10/25/2019 Approved EUGENE CASSIDY
Green Building Final 10/25/2019 Approved EUGENE CASSIDY
HVAC-Final 10/25/2019 Approved EUGENE CASSIDY
PLUMBING-Final 10/25/2019 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/25/2019 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/25/2019 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 10/25/2019 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/31/2019 Approved EUGENE CASSIDY
Final 10/31/2019 Corrections Issued EUGENE CASSIDY
Service/Power Release 10/31/2019 Not Ready for Inspection EUGENE CASSIDY
Final 11/26/2019 Not Ready for Inspection EUGENE CASSIDY
Final 1/2/2020 Corrections Issued EUGENE CASSIDY
Final 1/8/2020 OK to Issue CofO EUGENE CASSIDY
ELECTRICAL-Final 1/9/2020 Approved EUGENE CASSIDY
Service/Power Release 1/9/2020 Approved EUGENE CASSIDY