4606 S ORCHARD AVE 90037
Certificate Information: 4606 S ORCHARD AVE 90037
- Application / Permit
- 18014-70000-03354
- Plan Check / Job No.
- B18SL00881
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) GARAGE AND CONVERT ENTIRE BUILDING TO ADU PER AB 494 & SB 229; (N) ATTACHED TRELLIS. "COMPLY WITH DEPARTMENT ORDER effective date 01/23/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 7/2/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 5/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2018 | APPLICANT |
| Green Plans Picked Up | 7/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2018 | HELEN NGUYEN |
| Corrections Issued | 8/6/2018 | HELEN NGUYEN |
| Quality Review Completed | 8/7/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 8/24/2018 | APPLICANT |
| Applicant returned to address corrections | 11/13/2018 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/17/2018 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/27/2018 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/3/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/18/2019 | HELEN NGUYEN |
| Plan Check Approved | 6/27/2019 | HELEN NGUYEN |
| Issued | 7/2/2019 | LADBS |
| CofO in Progress | 4/24/2020 | MARIO CUEVAS |
| Permit Finaled | 5/11/2020 | BRUCE TODD |
| CofO Issued | 5/11/2020 | BRUCE TODD |
| Permit Finaled | 5/11/2020 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2018 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2019 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 1/14/2019 | GILBERT URREA |
| Low Impact Development | Cleared | 1/14/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/14/2019 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 1/14/2019 | MICHAEL CASTILLO |
| Green Code | Cleared | 2/6/2019 | SARAH ABOULHOSN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 8/1/2019 | Approved | SAMUEL PORTILLO |
| Deputy Drilled-In Anchors | 8/27/2019 | No Access for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 8/29/2019 | Corrections Issued | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 9/9/2019 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/9/2019 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/24/2019 | Corrections Issued | MARIO CUEVAS |
| ELECTRICAL-Rough | 10/24/2019 | Corrections Issued | MARIO CUEVAS |
| Green Building Rough | 10/24/2019 | Corrections Issued | MARIO CUEVAS |
| HVAC-Rough | 10/24/2019 | Corrections Issued | MARIO CUEVAS |
| PLUMBING-Rough | 10/24/2019 | Corrections Issued | MARIO CUEVAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2019 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Insulation | 11/18/2019 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 11/18/2019 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 11/21/2019 | Not Ready for Inspection | MARIO CUEVAS |
| ELECTRICAL-Rough | 11/21/2019 | Not Ready for Inspection | MARIO CUEVAS |
| Green Building Rough | 11/21/2019 | Not Ready for Inspection | MARIO CUEVAS |
| HVAC-Rough | 11/21/2019 | Not Ready for Inspection | MARIO CUEVAS |
| PLUMBING-Rough | 11/21/2019 | Not Ready for Inspection | MARIO CUEVAS |
| BUILDING-Rough-Frame | 1/22/2020 | Approved | MARIO CUEVAS |
| Green Building Rough | 1/22/2020 | Approved | MARIO CUEVAS |
| Rough-Elec/Plmb/HVAC | 1/22/2020 | Approved | MARIO CUEVAS |
| Insulation | 1/23/2020 | Approved | MARIO CUEVAS |
| Drywall Nailing | 2/4/2020 | Approved | MARIO CUEVAS |
| Interior/Exterior Lathing | 2/4/2020 | Approved | MARIO CUEVAS |
| ELECTRICAL-Final | 3/25/2020 | Corrections Issued | MARIO CUEVAS |
| Final | 3/25/2020 | Not Ready for Inspection | MARIO CUEVAS |
| Footing/Foundation/Slab | 3/25/2020 | Approved | MARIO CUEVAS |
| Green Building Final | 3/25/2020 | Not Ready for Inspection | MARIO CUEVAS |
| HVAC-Final | 3/25/2020 | Corrections Issued | MARIO CUEVAS |
| PLUMBING-Final | 3/25/2020 | Approved | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 3/25/2020 | SGSOV Not Ready | MARIO CUEVAS |
| Service/Power Release | 3/25/2020 | Not Required | MARIO CUEVAS |
| Smoke Detectors | 3/25/2020 | Approved | MARIO CUEVAS |
| Final | 4/14/2020 | Conditional Approval | MARIO CUEVAS |
| Green Building Final | 4/14/2020 | Approved | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 4/14/2020 | SGSOV Approved | MARIO CUEVAS |