7824 S DALTON AVE 90047

Certificate Information: 7824 S DALTON AVE 90047

Application / Permit
18014-70000-03236
Plan Check / Job No.
B18SL00859
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY DETACHED ADU AT REAR OF LOT.
Permit Issued
Issued on 12/3/2020
Issuing Office
Current Status
CofO Issued on 2/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2018 APPLICANT
Green Plans Picked Up 6/26/2018 APPLICANT
Assigned to Plan Check Engineer 7/5/2018 JOE VO
Corrections Issued 7/9/2018 JOE VO
Quality Review Completed 7/10/2018 GARO TELMI
Building Plans Picked Up 7/13/2018 APPLICANT
Applicant returned to address corrections 12/17/2018 JOE VO
Plan Check Approved 4/1/2019 JOE VO
Issued 12/3/2020 APPLICANT
CofO in Progress 2/19/2026 JOHN QUINTANILLA
Permit Finaled 2/22/2026 DEROLD HAUFF
CofO Issued 2/22/2026 DEROLD HAUFF
Permit Finaled 2/22/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/27/2018 JEANETTE VONG
Low Impact Development Cleared 11/27/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 11/27/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 11/30/2018 ROBYN STEELE
Sewer availability Cleared 11/30/2018 ROBYN STEELE
Green Code Cleared 12/17/2018 SARAH ABOULHOSN
Hydrant and Access approval Cleared 12/17/2018 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/8/2021 Corrections Issued EUGENE CASSIDY
Sewer 1/12/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 1/12/2021 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 6/15/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 6/15/2021 Conditional Approval FREDDIE RIVERA
Pre-Inspection 6/15/2021 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 7/9/2021 Approved EUGENE CASSIDY
Footing/Foundation/Slab 7/9/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/22/2021 Partial Approval DANIEL GONZALEZ
Gas Test 10/22/2021 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 10/22/2021 Partial Approval DANIEL GONZALEZ
Insulation 11/1/2021 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Approval JOAQUIN GREENOUGH
Pre-Inspection 2/28/2022 Partial Inspection LILIANA PORTILLO
ELECTRICAL-Rough 3/17/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Approved HORACE FULTZ
HVAC-Rough 3/17/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 5/2/2022 Corrections Issued HORACE FULTZ
Green Building Rough 5/2/2022 Not Ready for Inspection HORACE FULTZ
Verify Sprinkler Sign Off 5/2/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 6/10/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 6/10/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 6/27/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 7/7/2022 Approved HORACE FULTZ
PLUMBING-Rough 8/8/2022 Corrections Issued LILIANA PORTILLO
Insulation 8/29/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 8/29/2022 Approved LILIANA PORTILLO
Drywall Nailing 9/14/2022 Not Ready for Inspection LILIANA PORTILLO
Drywall Nailing 9/23/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/4/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 12/5/2022 Corrections Issued LILIANA PORTILLO
Underground Mechanical 12/5/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/21/2022 Approved LILIANA PORTILLO
Service/Power Release 1/31/2023 Partial Approval LILIANA PORTILLO
Shower Pan 5/12/2023 Approved MICHAEL LEWIS
Sewer 3/17/2025 No Access for Inspection JOHN QUINTANILLA
Service/Power Release 4/14/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 10/14/2025 Approved JOHN QUINTANILLA
Final 10/14/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 10/14/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 10/14/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 10/14/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 10/21/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 10/21/2025 Approved JOHN QUINTANILLA
HVAC-Final 10/21/2025 Approved JOHN QUINTANILLA
Smoke Detectors 10/21/2025 Approved JOHN QUINTANILLA
Final 11/20/2025 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Not Ready JOHN QUINTANILLA
Final 12/5/2025 Conditional Approval JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Approved JOHN QUINTANILLA
Final 2/10/2026 OK to Issue CofO JOHN QUINTANILLA