6025 S FIGUEROA ST 90003

Certificate Information: 6025 S FIGUEROA ST 90003

Application / Permit
18014-70000-02475
Plan Check / Job No.
B18SL00669
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
SECOND STORY ADDITION TO (E) CHURCH FOR CONFERENCE ROOM/MEETING ROOMS. SEE COMMENTS.
Permit Issued
Issued on 1/10/2020
Issuing Office
Metro
Current Status
Issued on 1/10/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/7/2018 APPLICANT
Disabled Access Plans Picked Up 6/7/2018 APPLICANT
Green Plans Picked Up 6/7/2018 APPLICANT
Assigned to Plan Check Engineer 6/14/2018 JEFFREY TANGONAN
Corrections Issued 6/22/2018 JEFFREY TANGONAN
Quality Review Completed 6/27/2018 CHON CHIO KUO
Building Plans Picked Up 7/2/2018 APPLICANT
Plan Check Approved 12/30/2019 JEFFREY TANGONAN
Issued 1/10/2020 LADBS

Permit Application Clearance Information

Project located in CRA area Cleared 9/19/2018 JIM URQUHART
Eng Process Fee Ord 176,300 Cleared 5/13/2019 JEANIE LAM
Sewer availability Cleared 5/13/2019 JEANIE LAM
DAS Clearance Cleared 6/6/2019 SHINE LIN
Green Code Cleared 6/6/2019 NEGAR NEJAD
Low Impact Development Cleared 10/11/2019 SARAH YOUSSEF
Food establishment approval Cleared 11/14/2019 LACDHS APPROVED
Roof/Waste drainage to street Cleared 11/25/2019 EMIL KYUPELYAN
Comm Cor/Mini-Mall Cleared 12/18/2019 ANNA VAN
Fire Marshall Fire Life Safety Cleared 12/23/2019 WILLIAM JOHNS

Contact Information

Architect Thomas,, Roy J; Lic. No.: C28368 6200 MORNING PLACE      ALTA LOMA, CA 91737
Contractor Owner-Builder       ,
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/6/2020 Corrections Issued RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Rough 9/29/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 9/29/2020 Partial Approval LEOPOLDO MENDOZA
Interior/Exterior Lathing 3/9/2021 Approved TIMOTHY BUXTON
Green Building Rough 4/21/2021 Partial Approval LANNY MERRICK
Wood Frame 4/21/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 5/3/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Rough 5/3/2021 Approved LEOPOLDO MENDOZA
Insulation 5/3/2021 Approved LEOPOLDO MENDOZA
Wood Frame 5/3/2021 Approved LEOPOLDO MENDOZA
Drywall Nailing 6/14/2021 Partial Approval LEOPOLDO MENDOZA