638 W 104TH ST 90044
Certificate Information: 638 W 104TH ST 90044
- Application / Permit
- 18014-70000-02319
- Plan Check / Job No.
- B18SL00622
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE 24'X24'-3" SECOND STORY ACCESSORY DWELLING (PER LAMC 12.22 A.33(c) and (d)) ADDITION OVER (E) GARAGE. "COMPLY WITH DEPARTMENT ORDER effective date 04/01/2014. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". [SEE COMMENTS]
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2018 | APPLICANT |
| Green Plans Picked Up | 5/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2018 | YAQUB MIRZA |
| Corrections Issued | 5/30/2018 | YAQUB MIRZA |
| Quality Review Completed | 6/4/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 6/7/2018 | APPLICANT |
| Applicant returned to address corrections | 2/26/2021 | DAWN MC NULTY |
| Plan Check Approved | 3/22/2021 | DAWN MC NULTY |
| Issued | 3/22/2021 | APPLICANT |
| CofO in Progress | 9/15/2022 | JOHN KLARIN |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2018 | PAMELA TENEZA |
| Hydrant and Access approval | Cleared | 7/17/2018 | GILBERT URREA |
| Sewer availability | Cleared | 7/17/2018 | PAMELA TENEZA |
| Low Impact Development | Cleared | 8/31/2018 | RYAN HUDSON |
| Green Code | Cleared | 9/5/2018 | NEGAR NEJAD |
| Roof/Waste drainage to street | Cleared | 9/18/2020 | RENZ SORIANO |
| Construction within easement | Cleared | 1/29/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/9/2021 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 5/25/2021 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 12/16/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/18/2022 | Not Ready for Inspection | KIM DOEPPING |
| ELECTRICAL-Rough | 1/25/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/7/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/7/2022 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 4/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/7/2022 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 4/14/2022 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 4/15/2022 | Approved | JOHN KLARIN |
| Deputy Drilled-In Anchors | 4/19/2022 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 4/26/2022 | Not Ready for Inspection | JOHN KLARIN |
| Deputy Drilled-In Anchors | 4/28/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 4/29/2022 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 4/29/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 4/29/2022 | Approved | JOHN KLARIN |
| Sewer | 4/29/2022 | Approved | JOHN KLARIN |
| Insulation | 5/5/2022 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 5/6/2022 | No Result Entered | MARK HATFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/24/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/24/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 6/24/2022 | Approved | JOHN KLARIN |
| Final | 6/24/2022 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 6/24/2022 | Approved | JOHN KLARIN |
| Green Building Final | 6/24/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 6/24/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 6/24/2022 | Approved | JOHN KLARIN |
| Final | 7/1/2022 | Corrections Issued | JOHN KLARIN |
| Final | 9/14/2022 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 9/14/2022 | Approved | JOHN KLARIN |