FIRST AND SECOND FLOOR ADDITION IN SINGLE FAMILY BUILDING AT REAR YEARD
Permit Issued
Issued on 11/15/2018
Issuing Office
South Los Angeles
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2018 APPLICANT
Green Plans Picked Up 4/19/2018 APPLICANT
Assigned to Plan Check Engineer 4/23/2018 AUNG SOE
Corrections Issued 4/27/2018 AUNG SOE
Quality Review Completed 5/4/2018 ARMEN JIVALAGIAN
Building Plans Picked Up 5/10/2018 APPLICANT
Plan Check Approved 11/9/2018 AUNG SOE
Issued 11/15/2018 LADBS
CofO in Progress 6/21/2025 DAVID FEILER
Permit Finaled 6/23/2025 RICHARD STEINBACH
CofO Issued 6/23/2025 RICHARD STEINBACH
Permit Finaled 6/23/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/22/2018 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 5/22/2018 GILBERT URREA
Sewer availability Cleared 5/22/2018 ADRIAN SANCHEZ
Green Code Cleared 8/28/2018 NEGAR NEJAD
Low Impact Development Cleared 9/18/2018 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/18/2018 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/31/2018 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 1/15/2019 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 7/8/2019 Corrections Issued WILLIAM ROSE
Footing/Foundation/Slab 8/5/2019 Not Ready for Inspection WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 8/6/2019 Approved WILLIAM ROSE
BUILDING-Rough-Frame 11/1/2019 Corrections Issued WILLIAM ROSE
Green Building Rough 11/1/2019 Not Ready for Inspection WILLIAM ROSE
Rough-Elec/Plmb/HVAC 11/1/2019 Corrections Issued WILLIAM ROSE
BUILDING-Rough-Frame 11/22/2019 Not Ready for Inspection WILLIAM ROSE
Green Building Rough 11/22/2019 Not Ready for Inspection WILLIAM ROSE
Rough-Elec/Plmb/HVAC 11/22/2019 Not Ready for Inspection WILLIAM ROSE
Pre-Inspection 12/6/2019 Corrections Issued WILLIAM ROSE
ELECTRICAL-Rough 4/15/2020 Approved EUGENE CASSIDY
HVAC-Final 4/15/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/30/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 11/30/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/30/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 11/30/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 11/30/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 12/9/2020 Approved EUGENE CASSIDY
Green Building Rough 12/9/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 12/9/2020 Approved EUGENE CASSIDY
Drywall Nailing 7/2/2021 Approved EUGENE CASSIDY
Final 7/2/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/2/2021 Approved EUGENE CASSIDY
Green Building Final 7/2/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/2/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 7/2/2021 Not Ready for Inspection EUGENE CASSIDY
Final 2/22/2022 Corrections Issued JOHN KLARIN
Green Building Final 2/22/2022 Approved JOHN KLARIN
Smoke Detectors 2/22/2022 Approved JOHN KLARIN
Final 9/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 9/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 12/23/2022 Corrections Issued JOHN KLARIN
Final 1/6/2023 Corrections Issued JOHN KLARIN
Final 1/13/2023 Not Ready for Inspection JOHN KLARIN
Final 2/1/2023 Not Ready for Inspection JOHN KLARIN
Final 6/21/2025 OK to Issue CofO DAVID FEILER