1731 S WELLESLEY AVE 90025

Certificate Information: 1731 S WELLESLEY AVE 90025

Application / Permit
18014-70000-00469
Plan Check / Job No.
B18SL00127
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION AND ADDITION TO (E) 345 SF GARAGE TO 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 1/14/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2018 APPLICANT
Assigned to Plan Check Engineer 2/22/2018 JEFFREY MACHADO
Green Plans Picked Up 3/5/2018 APPLICANT
Corrections Issued 3/6/2018 JEFFREY MACHADO
Quality Review Completed 3/15/2018 BILL STUTSMAN
Building Plans Picked Up 3/27/2018 APPLICANT
Plan Check Approved 7/3/2018 JEFFREY MACHADO
Issued 1/14/2019 LADBS
CofO in Progress 2/12/2020 OGANES TARAKHCHYAN
Permit Finaled 6/30/2020 VINCENT COTTON
CofO Issued 6/30/2020 VINCENT COTTON
Permit Finaled 6/30/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 4/25/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/4/2018 NAZILA NOORIFAR
Sewer availability Cleared 5/4/2018 NAZILA NOORIFAR
Green Code Cleared 6/27/2018 COLIN LOREDO
Low Impact Development Cleared 6/28/2018 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 6/28/2018 STEVE MELGAR

Contact Information

Contractor Arbabi M R David; Lic. No.: 514421-B 9613 KESSLER AVENUE      CHATSWORTH, CA 91311
Engineer Cooke, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/25/2019 Not Ready for Inspection ROBERT VORHIS
Pre-Inspection 2/25/2019 Corrections Issued ROBERT VORHIS
BUILDING-Rough-Frame 4/12/2019 Corrections Issued EVAN COOPER
Green Building Rough 4/12/2019 Not Ready for Inspection EVAN COOPER
HVAC-Rough 4/12/2019 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 5/2/2019 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 6/14/2019 Corrections Issued ROBERT SHELLY
ELECTRICAL-Rough 6/14/2019 Not Ready for Inspection ROBERT SHELLY
Green Building Rough 6/14/2019 Not Ready for Inspection ROBERT SHELLY
PLUMBING-Rough 6/14/2019 Not Ready for Inspection ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 6/18/2019 Not Ready for Inspection EVAN COOPER
Insulation 6/21/2019 Not Ready for Inspection ROBERT SHELLY
BUILDING-Rough-Frame 7/19/2019 Approved ROBERT SHELLY
Green Building Rough 7/19/2019 Approved ROBERT SHELLY
Insulation 7/19/2019 Approved ROBERT SHELLY
Rough-Elec/Plmb/HVAC 7/19/2019 Approved ROBERT SHELLY
Drywall Nailing 7/26/2019 Approved ROBERT SHELLY
Interior/Exterior Lathing 7/26/2019 Partial Approval ROBERT SHELLY
Final 11/21/2019 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/21/2019 Approved OGANES TARAKHCHYAN
Green Building Final 11/21/2019 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/21/2019 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 11/21/2019 Approved OGANES TARAKHCHYAN
Final 12/6/2019 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/6/2019 SGSOV Approved OGANES TARAKHCHYAN
Final 1/3/2020 Partial Approval OGANES TARAKHCHYAN
Service/Power Release 1/13/2020 Approved OGANES TARAKHCHYAN
Final 2/11/2020 Partial Approval OGANES TARAKHCHYAN